Withdrawn queue requests in the USA (2018 requests) β€” page 29

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,424226.5 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,424 requests Β· page 29 of 29
ProjectCapacityStatusLocationRegionQueuedOnline
South Jefferson Road Storage
Battery storage
2.0 MWWithdrawn / abandoned Morris, NJPJM Mar 2018target 2020
Solar project 19603, Greenwood County
Solar
2.0 MWWithdrawn / abandoned Greenwood, SCSoutheast Jan 2018
Solar project TCS-15, Yakima County
Solar Β· OneEnergy Development, LLC
2.0 MWWithdrawn / abandoned Yakima, WAWest Oct 2018target 2024
Solar project AE1-223, Burlington County
Solar
1.9 MWWithdrawn / abandoned Burlington, NJPJM Sep 2018target 2018
Solar project 533, Twin Falls County
Solar
1.7 MWWithdrawn / abandoned Twin Falls, IDWest May 2018
Solar project AE1-011
Solar
1.5 MWWithdrawn / abandoned MDPJM May 2018target 2019
Astoria Storage on Demand
Battery storage Β· Consolidated Edison Co. of NY, Inc.
1.5 MWWithdrawn / abandoned Queens, NYNYISO Jul 2018
Hydro project LGE-GIS-2018-008, Estill County
Hydro
1.5 MWWithdrawn / abandoned Estill, KYSoutheast Oct 2018target 2018
5203 Saint Barnabas Road
Solar
1.4 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2022
Solar project AE1-082, Charles County
Solar
1.3 MWWithdrawn / abandoned Charles, MDPJM Aug 2018target 2018
Solar project AD2-064, Camden County
Solar
1.3 MWWithdrawn / abandoned Camden, NJPJM Feb 2018target 2019
Solar project AE1-016, Prince George's County
Solar
1.1 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2019
Onshore wind project J1126, Tuscola County
Onshore wind
1.1 MWWithdrawn / abandoned Tuscola, MIMISO Mar 2018target 2020
Solar project G0594, Lane County
Solar
1.0 MWWithdrawn / abandoned Lane, ORWest Jul 2018target 2018
Solar project AE1-043, Gloucester County
Solar
1.0 MWWithdrawn / abandoned Gloucester, NJPJM Jul 2018target 2018
Battery storage project AE1-048, Queen Anne's County
Battery storage
1.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Jul 2018
Bethlehem Solar
Solar Β· PSEG Power NY LLC
1.0 MWWithdrawn / abandoned Albany, NYNYISO May 2018
4179 Suitland Road
Solar
0.9 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2022
Solar project 1007, Wallowa County
Solar
0.9 MWWithdrawn / abandoned Wallowa, ORWest Mar 2018target 2019
UD Motor Pool
Battery storage
0.8 MWWithdrawn / abandoned New Castle, DEPJM Feb 2018target 2022
State Route 57 Solar
Solar
0.8 MWWithdrawn / abandoned Warren, NJPJM Dec 2018target 2021
Solar project AE1-014, Prince George's County
Solar
0.5 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2019
1724 64th Street
Solar
0.5 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2018target 2022
Solar project 1026, Salt Lake County
Solar
0.4 MWWithdrawn / abandoned Salt Lake, UTWest May 2018target 2018
Page 29 of 29

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)