United States › Grid › Interconnection queues › New Jersey

BATTERY STORAGE · PJM

South Jefferson Road Storage

South Jefferson Road Storage is a 2.0 MW battery storage request withdrawn in the PJM interconnection queue, in Morris County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD2-210
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Cedar Knolls 12.5 kV
Location
Morris County, New Jersey
Technology
Battery: 2.0 MW
Total requested
2.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
30 March 2018
Proposed online date
December 2020
Withdrawn
November 2023

Location

Marker shows the centre of Morris County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Morris County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem