Solar project AE1-223, Burlington County

Solar project AE1-223, Burlington County is a 1.9 MW solar request withdrawn in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2018 (completed)
  2. Withdrawn / abandonedJun 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE1-223
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Allentown Booster 138 kV
Location
Burlington County, New Jersey
Technology
Solar: 1.9 MW
Total requested
1.9 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
28 September 2018
Proposed online date
November 2018
Withdrawn
June 2019

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.