United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Southeast (non-ISO utilities) — page 27
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project IC-287, Etowah County Onshore wind |
80.5 MW | Withdrawn / abandoned |
| Solar project IC-671, Evans County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 570306, Franklin County Solar · Masked |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-1093, Lowndes County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project GI-89, Scott County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-915, Autauga County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-785, Calhoun County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 568978, Duplin County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 8609, Clarendon County Solar · Masked |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-45, Jasper County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-914, Autauga County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-427, Montgomery County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 896943, Wayne County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-983, Mobile County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-913, Autauga County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-998, Baldwin County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-433, Perry County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-887, Talladega County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 20318, Onslow County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-675, Geneva County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 328, Colbert County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 909227, Richmond County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-546, Washington County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-1171, Greene County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-413, Dale County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 897025, Scotland County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-927, Perry County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 569984, Craven County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-1017, Clarke County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-750, Perry County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-783, Clarke County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-1131, Blount County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-1109, Mobile County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 920609, Wayne County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-1020, Lowndes County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 20841, Craven County Solar · Masked |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-912, Autauga County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-746, Escambia County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 67146, Darlington County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-1062, Marengo County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 563066, Wayne County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 920637, Scotland County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-1092, Lowndes County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 977268, Bladen County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project 226, Kershaw County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-1110, Mobile County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project 380E, Jackson County Solar · Third Party |
80.0 MW | Withdrawn / abandoned |
| Solar project 569072, Davidson County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-893, Mobile County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-498, Dallas County Solar |
80.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)