Solar project IC-912, Autauga County

Solar project IC-912, Autauga County is a 80.0 MW solar request withdrawn in the Southeast interconnection queue, in Autauga County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2020 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-912
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Autaugaville Substation 230 kV Bus
Location
Autauga County, Alabama
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
13 November 2020
Withdrawn
May 2021

Location

Marker shows the centre of Autauga County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Autauga County