United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 23

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 23 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2004-3, Weld County
Onshore wind
275 MWWithdrawn / abandoned Weld, COWest Jul 2004target 2006
Gas project 359, Salt Lake County
Gas
275 MWWithdrawn / abandoned Salt Lake, UTWest Nov 2010target 2014
Solar + storage project C3-027, Juab County
Solar + storage
275 MWWithdrawn / abandoned Juab, UTWest May 2023target 2026
Other project 21, Gooding County
Other
275 MWWithdrawn / abandoned Gooding, IDWest Apr 2001target 2005
Solar + storage project C2-37, Juab County
Solar + storage
275 MWWithdrawn / abandoned Juab, UTWest Apr 2022target 2025
Solar project G0603, Garfield County
Solar
275 MWWithdrawn / abandoned Garfield, WAWest Oct 2018target 2022
Other project 19, Lincoln County
Other
275 MWWithdrawn / abandoned Lincoln, IDWest Apr 2001target 2005
Gas project 377, Salt Lake County
Gas
275 MWWithdrawn / abandoned Salt Lake, UTWest Mar 2011target 2014
Other project 1, Canyon County
Other
273 MWWithdrawn / abandoned Canyon, IDWest Jan 2001target 2005
Onshore wind project 297, Twin Falls County
Onshore wind
272 MWWithdrawn / abandoned Twin Falls, IDWest Sep 2009
Battery storage project Q2411, Pinal County
Battery storage
271 MWWithdrawn / abandoned Pinal, AZWest Feb 2024target 2028
Coal project 121, Sevier County
Coal · PacifiCorp Commercial & Trading
270 MWWithdrawn / abandoned Sevier, UTWest Feb 2007target 2009
Solar + storage project C2-174, Benton County
Solar + storage
270 MWWithdrawn / abandoned Benton, WAWest May 2022target 2025
Gas project GI-2008-34, Elbert County
Gas
270 MWWithdrawn / abandoned Elbert, COWest Dec 2008target 2011
Gas project GI-2008-33, Morgan County
Gas
270 MWWithdrawn / abandoned Morgan, COWest Dec 2008target 2011
Onshore wind project GI-2010-2, Baca County
Onshore wind
268 MWWithdrawn / abandoned Baca, COWest Jan 2010target 2017
Coal project 32, Cascade County
Coal
268 MWWithdrawn / abandoned Cascade, MTWest Jul 2004target 2011
Frontier Technology
Gas
265 MWWithdrawn / abandoned Lane, ORWest Mar 2001target 2003
Gas project GI-2006-1c, Adams County
Gas
264 MWWithdrawn / abandoned Adams, COWest Jan 2006target 2007
Other project 580, Bingham County
Other · Arco Wind, LLC
263 MWWithdrawn / abandoned Bingham, IDWest May 2020target 2020
Gas project C3-107, Utah County
Gas
260 MWWithdrawn / abandoned Utah, UTWest May 2023target 2026
Solar project G1027, Umatilla County
Solar
260 MWWithdrawn / abandoned Umatilla, ORWest Nov 2023target 2028
Onshore wind project Company 233, Clark County
Onshore wind
260 MWWithdrawn / abandoned Clark, NVWest Sep 2022target 2026
Battery storage project Q536, Pinal County
Battery storage
259 MWWithdrawn / abandoned Pinal, AZWest Aug 2023target 2028
Gas project GI-2008-29, Weld County
Gas
256 MWWithdrawn / abandoned Weld, COWest Nov 2008target 2015
Solar project Company 152, Clark County
Solar
255 MWWithdrawn / abandoned Clark, NVWest Mar 2017target 2020
Solar + storage project Company IJ, Pershing County
Solar + storage
255 MWWithdrawn / abandoned Pershing, NVWest Mar 2018target 2021
Onshore wind project G0329, Garfield County
Onshore wind
252 MWWithdrawn / abandoned Garfield, WAWest May 2008target 2013
Onshore wind project G0328, Garfield County
Onshore wind
252 MWWithdrawn / abandoned Garfield, WAWest May 2008target 2012
Horizon Wind Energy-WRidge
Onshore wind · Wind Ridge Power Partners, LLC
252 MWWithdrawn / abandoned Kittitas, WAWest Jan 2003target 2004
Onshore wind project 232, Wallowa County
Onshore wind
252 MWWithdrawn / abandoned Wallowa, ORWest Feb 2008target 2010
Solar + storage project 1027, Tooele County
Solar + storage
251 MWWithdrawn / abandoned Tooele, UTWest May 2018target 2022
Solar + storage project 1028, Tooele County
Solar + storage
251 MWWithdrawn / abandoned Tooele, UTWest May 2018target 2022
RES North America LLC
Onshore wind · RES North America
250 MWWithdrawn / abandoned Sherman, ORWest Nov 2002target 2004
Solar + storage project 4, Sacramento County
Solar + storage
250 MWWithdrawn / abandoned Sacramento, CAWest Jun 2020target 2027
Solar + storage project Q426, Pinal County
Solar + storage
250 MWWithdrawn / abandoned Pinal, AZWest Sep 2021target 2025
Solar + storage project 703, Ada County
Solar + storage
250 MWWithdrawn / abandoned Ada, IDWest Feb 2023
Solar + storage project 561, Jerome County
Solar + storage
250 MWWithdrawn / abandoned Jerome, IDWest Jul 2019
Battery storage project Q429, Pinal County
Battery storage
250 MWWithdrawn / abandoned Pinal, AZWest Sep 2021target 2023
Solar + storage project GI-2023-6, Pueblo County
Solar + storage
250 MWWithdrawn / abandoned Pueblo, COWest May 2023target 2028
Battery storage project 28, Sacramento County
Battery storage
250 MWWithdrawn / abandoned Sacramento, CAWest Nov 2022target 2028
Onshore wind project G0499, Elmore County
Onshore wind
250 MWWithdrawn / abandoned Elmore, IDWest Sep 2014target 2017
Solar project Q296, Yavapai County
Solar
250 MWWithdrawn / abandoned Yavapai, AZWest Mar 2019target 2021
EC250W Project
Onshore wind
250 MWWithdrawn / abandoned Eddy, NMWest Mar 2018target 2020
Onshore wind project G0308, Gilliam County
Onshore wind
250 MWWithdrawn / abandoned Gilliam, ORWest Jan 2008target 2012
Onshore wind project G0277, Klickitat County
Onshore wind
250 MWWithdrawn / abandoned Klickitat, ORWest Jul 2007target 2010
Solar project GI-2008-32, Saguache County
Solar
250 MWWithdrawn / abandoned Saguache, COWest Dec 2008target 2013
Onshore wind project Q203, Coconino County
Onshore wind
250 MWWithdrawn / abandoned Coconino, AZWest Jul 2011target 2014
Solar + storage project GI-TC-2024-13, Routt County
Solar + storage
250 MWWithdrawn / abandoned Routt, COWest May 2024target 2027
Solar + storage project C3-018, Juab County
Solar + storage
250 MWWithdrawn / abandoned Juab, UTWest Apr 2023target 2025
Page 23 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)