United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in West (non-ISO utilities) — page 23
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GI-2004-3, Weld County Onshore wind |
275 MW | Withdrawn / abandoned |
| Gas project 359, Salt Lake County Gas |
275 MW | Withdrawn / abandoned |
| Solar + storage project C3-027, Juab County Solar + storage |
275 MW | Withdrawn / abandoned |
| Other project 21, Gooding County Other |
275 MW | Withdrawn / abandoned |
| Solar + storage project C2-37, Juab County Solar + storage |
275 MW | Withdrawn / abandoned |
| Solar project G0603, Garfield County Solar |
275 MW | Withdrawn / abandoned |
| Other project 19, Lincoln County Other |
275 MW | Withdrawn / abandoned |
| Gas project 377, Salt Lake County Gas |
275 MW | Withdrawn / abandoned |
| Other project 1, Canyon County Other |
273 MW | Withdrawn / abandoned |
| Onshore wind project 297, Twin Falls County Onshore wind |
272 MW | Withdrawn / abandoned |
| Battery storage project Q2411, Pinal County Battery storage |
271 MW | Withdrawn / abandoned |
| Coal project 121, Sevier County Coal · PacifiCorp Commercial & Trading |
270 MW | Withdrawn / abandoned |
| Solar + storage project C2-174, Benton County Solar + storage |
270 MW | Withdrawn / abandoned |
| Gas project GI-2008-34, Elbert County Gas |
270 MW | Withdrawn / abandoned |
| Gas project GI-2008-33, Morgan County Gas |
270 MW | Withdrawn / abandoned |
| Onshore wind project GI-2010-2, Baca County Onshore wind |
268 MW | Withdrawn / abandoned |
| Coal project 32, Cascade County Coal |
268 MW | Withdrawn / abandoned |
| Frontier Technology Gas |
265 MW | Withdrawn / abandoned |
| Gas project GI-2006-1c, Adams County Gas |
264 MW | Withdrawn / abandoned |
| Other project 580, Bingham County Other · Arco Wind, LLC |
263 MW | Withdrawn / abandoned |
| Gas project C3-107, Utah County Gas |
260 MW | Withdrawn / abandoned |
| Solar project G1027, Umatilla County Solar |
260 MW | Withdrawn / abandoned |
| Onshore wind project Company 233, Clark County Onshore wind |
260 MW | Withdrawn / abandoned |
| Battery storage project Q536, Pinal County Battery storage |
259 MW | Withdrawn / abandoned |
| Gas project GI-2008-29, Weld County Gas |
256 MW | Withdrawn / abandoned |
| Solar project Company 152, Clark County Solar |
255 MW | Withdrawn / abandoned |
| Solar + storage project Company IJ, Pershing County Solar + storage |
255 MW | Withdrawn / abandoned |
| Onshore wind project G0329, Garfield County Onshore wind |
252 MW | Withdrawn / abandoned |
| Onshore wind project G0328, Garfield County Onshore wind |
252 MW | Withdrawn / abandoned |
| Horizon Wind Energy-WRidge Onshore wind · Wind Ridge Power Partners, LLC |
252 MW | Withdrawn / abandoned |
| Onshore wind project 232, Wallowa County Onshore wind |
252 MW | Withdrawn / abandoned |
| Solar + storage project 1027, Tooele County Solar + storage |
251 MW | Withdrawn / abandoned |
| Solar + storage project 1028, Tooele County Solar + storage |
251 MW | Withdrawn / abandoned |
| RES North America LLC Onshore wind · RES North America |
250 MW | Withdrawn / abandoned |
| Solar + storage project 4, Sacramento County Solar + storage |
250 MW | Withdrawn / abandoned |
| Solar + storage project Q426, Pinal County Solar + storage |
250 MW | Withdrawn / abandoned |
| Solar + storage project 703, Ada County Solar + storage |
250 MW | Withdrawn / abandoned |
| Solar + storage project 561, Jerome County Solar + storage |
250 MW | Withdrawn / abandoned |
| Battery storage project Q429, Pinal County Battery storage |
250 MW | Withdrawn / abandoned |
| Solar + storage project GI-2023-6, Pueblo County Solar + storage |
250 MW | Withdrawn / abandoned |
| Battery storage project 28, Sacramento County Battery storage |
250 MW | Withdrawn / abandoned |
| Onshore wind project G0499, Elmore County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project Q296, Yavapai County Solar |
250 MW | Withdrawn / abandoned |
| EC250W Project Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project G0308, Gilliam County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project G0277, Klickitat County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project GI-2008-32, Saguache County Solar |
250 MW | Withdrawn / abandoned |
| Onshore wind project Q203, Coconino County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar + storage project GI-TC-2024-13, Routt County Solar + storage |
250 MW | Withdrawn / abandoned |
| Solar + storage project C3-018, Juab County Solar + storage |
250 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)