United States › Grid › Interconnection queues › Oregon
ONSHORE WIND · WESTRES North America LLC
RES North America LLC is a 250 MW onshore wind request withdrawn in the West interconnection queue, in Sherman County, Oregon, connecting to RES North America.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2002 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G113
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- RES North America
- Developer
- RES North America
- Connection point (POI)
- John Day Substation
- Location
- Sherman County, Oregon
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 20 November 2002
- Proposed online date
- June 2004
Location
Marker shows the centre of Sherman County; the queue data does not give exact sites.
Other requests in Sherman County
- Other project G0864, Sherman CountyOther · 1,304 MW · in study
- Solar + storage project G0795, Sherman CountySolar + storage · 1,300 MW · in study
- Solar + storage project G0791, Sherman CountySolar + storage · 1,300 MW · in study
- Solar + storage project G0615, Sherman CountySolar + storage · 1,200 MW · in study
- Solar project G0687, Sherman CountySolar · 900 MW · in study
- Solar + storage project G0825, Sherman CountySolar + storage · 800 MW · in study
- Solar + storage project G0850, Sherman CountySolar + storage · 800 MW · in study
- Solar + storage project G0849, Sherman CountySolar + storage · 800 MW · in study
- Wind + storage project G1041, Sherman CountyWind + storage · 750 MW · in study
- Battery storage project G0948, Sherman CountyBattery storage · 650 MW · in study
- Battery storage project G0947, Sherman CountyBattery storage · 650 MW · in study
- Battery storage project G0796, Sherman CountyBattery storage · 650 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem