United States βΊ Grid βΊ Interconnection queues βΊ California
SOLAR + STORAGE Β· WESTSolar + storage project 4, Sacramento County
Solar + storage project 4, Sacramento County is a 250 MW solar + storage request withdrawn in the West interconnection queue, in Sacramento County, California, connecting to Sacramento Municipal Utility District.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 4
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Sacramento Municipal Utility District
- Connection point (POI)
- New substation near Elverta 230kV Substation
- Location
- Sacramento County, California
- Technology
- Solar: 250 MW Β· Battery
- Total requested
- 250 MW
- Study phase
- Facility Study
- Queue status
- Withdrawn
- Entered queue
- 30 June 2020
- Proposed online date
- August 2027
Location
Marker shows the centre of Sacramento County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Sacramento County
- Solar + storage project 20, Sacramento CountySolar + storage Β· 550 MW Β· in study
- Other project SC1Q31, Sacramento CountyOther Β· 400 MW Β· in study
- Solar + storage project 8, Sacramento CountySolar + storage Β· 344 MW Β· in study
- Solar + storage project 26, Sacramento CountySolar + storage Β· 275 MW Β· in study
- Other project SC1Q33, Sacramento CountyOther Β· 250 MW Β· in study
- Solar + storage project 12, Sacramento CountySolar + storage Β· 250 MW Β· in study
- Solar + storage project 3, Sacramento CountySolar + storage Β· 250 MW Β· in study
- Battery storage project 16, Sacramento CountyBattery storage Β· 204 MW Β· in study
- Battery storage project SC1Q32, Sacramento CountyBattery storage Β· 200 MW Β· in study
- Battery storage project 11, Sacramento CountyBattery storage Β· 200 MW Β· in study
- Battery storage project 22, Sacramento CountyBattery storage Β· 160 MW Β· in study
- Solar + storage project 30, Sacramento CountySolar + storage Β· 156 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem