OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 20

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 20 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Q233, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Mar 2016target 2021
Solar + storage project C1-59, Converse County
Solar + storage
300 MWWithdrawn / abandoned Converse, WYWest May 2021target 2024
Solar project 572, Jerome County
Solar
300 MWWithdrawn / abandoned Jerome, IDWest Nov 2019
Battery storage project G0938, Benton County
Battery storage
300 MWWithdrawn / abandoned Benton, WAWest Sep 2023target 2027
Solar + storage project C3-124, Juab County
Solar + storage
300 MWWithdrawn / abandoned Juab, UTWest May 2023target 2027
Onshore wind project C3-104, Bingham County
Onshore wind
300 MWWithdrawn / abandoned Bingham, IDWest May 2023target 2028
Solar + storage project 764, Minidoka County
Solar + storage
300 MWWithdrawn / abandoned Minidoka, IDWest Mar 2025
Solar + storage project Q385, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Mar 2021target 2025
Solar project Q32, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Aug 2007target 2010
Other project IA-PNM-2014-01, Guadalupe Cty County
Other
300 MWWithdrawn / abandoned Guadalupe Cty, NMWest Feb 2014target 2015
Onshore wind project G0296, Morrow County
Onshore wind
300 MWWithdrawn / abandoned Morrow, ORWest Oct 2007target 2012
Solar project 1049, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Solar + storage project 1220, Klamath County
Solar + storage
300 MWWithdrawn / abandoned Klamath, ORWest Apr 2020target 2023
Solar project GI-2021-21, Pueblo County
Solar
300 MWWithdrawn / abandoned Pueblo, COWest Oct 2021target 2024
Solar + storage project Company KE, Churchill County
Solar + storage
300 MWWithdrawn / abandoned Churchill, NVWest Sep 2019target 2022
Solar + storage project Q15, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Sep 2020target 2023
HI300SB Project
Solar + storage
300 MWWithdrawn / abandoned Grant, NMWest Mar 2020target 2022
Solar project 1050, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Onshore wind project GI-2008-2, Huerfano County
Onshore wind
300 MWWithdrawn / abandoned Huerfano, COWest Mar 2008target 2009
Gas project 498, Sweetwater County
Gas
300 MWWithdrawn / abandoned Sweetwater, WYWest Jun 2013target 2016
Onshore wind project GI-2003-1, Morgan County
Onshore wind
300 MWWithdrawn / abandoned Morgan, COWest Oct 2003target 2006
Battery storage project C3-045, Box Elder County
Battery storage · PacifiCorp
300 MWWithdrawn / abandoned Box Elder, UTWest May 2023target 2030
Solar + storage project C3-142, Tooele County
Solar + storage
300 MWWithdrawn / abandoned Tooele, UTWest May 2023target 2028
Onshore wind project G0298, Columbia County
Onshore wind
300 MWWithdrawn / abandoned Columbia, WAWest Nov 2007target 2009
Solar + storage project CS23-05, Adams County
Solar + storage
300 MWWithdrawn / abandoned Adams, WAWest Apr 2023target 2026
Solar + storage project GI-2022-12, Pueblo County
Solar + storage
300 MWWithdrawn / abandoned Pueblo, COWest Apr 2022target 2025
Battery storage project C2-51, Clark County
Battery storage · PacifiCorp
300 MWWithdrawn / abandoned Clark, WAWest May 2022target 2028
Solar + storage project 648, Power County
Solar + storage · NextEra Energy Resources Interconnection Holdings, LLC
300 MWWithdrawn / abandoned Power, IDWest Mar 2022
Solar + storage project C3-101, Millard County
Solar + storage
300 MWWithdrawn / abandoned Millard, UTWest May 2023target 2026
Solar + storage project C3-105, Bannock County
Solar + storage
300 MWWithdrawn / abandoned Bannock, IDWest May 2023target 2027
300MW Lower Monumental-Starbuck
Onshore wind · RES North America
300 MWWithdrawn / abandoned Columbia, WAWest Sep 2001target 2004
Battery storage project G1042, Sherman County
Battery storage
300 MWWithdrawn / abandoned Sherman, ORWest Nov 2023target 2027
Onshore wind project 130, Carbon County
Onshore wind
300 MWWithdrawn / abandoned Carbon, WYWest Apr 2007target 2011
Solar project G0632, Grant County
Solar
300 MWWithdrawn / abandoned Grant, WAWest Nov 2019target 2022
Onshore wind project 925, Platte County
Onshore wind
300 MWWithdrawn / abandoned Platte, WYWest Aug 2017target 2020
Onshore wind project G0271, Yakima County
Onshore wind
300 MWWithdrawn / abandoned Yakima, WAWest May 2007target 2009
Gas project 222, Converse County
Gas · PacifiCorp Energy
300 MWWithdrawn / abandoned Converse, WYWest May 2008target 2011
Onshore wind project GI-0810, Meade County
Onshore wind
300 MWWithdrawn / abandoned Meade, SDWest May 2008target 2012
Solar + storage project Q248, Maricopa County
Solar + storage
300 MWWithdrawn / abandoned Maricopa, AZWest Sep 2016target 2021
Onshore wind project Q05, Kern County
Onshore wind
300 MWWithdrawn / abandoned Kern, CAWest Feb 2008target 2016
Onshore wind project GI-0114, Mcintosh County
Onshore wind
300 MWWithdrawn / abandoned Mcintosh, NDWest Nov 2001
Onshore wind project GI-0115, Mcintosh County
Onshore wind
300 MWWithdrawn / abandoned Mcintosh, NDWest Nov 2001
Onshore wind project GI-2004-9, Elbert County
Onshore wind
300 MWWithdrawn / abandoned Elbert, COWest Sep 2004target 2006
Onshore wind project 2007-G4
Onshore wind
300 MWWithdrawn / abandoned West Mar 2007target 2014
Onshore wind project Q525, Mohave County
Onshore wind
300 MWWithdrawn / abandoned Mohave, AZWest Mar 2023target 2027
Onshore wind project G0981, Sherman County
Onshore wind
300 MWWithdrawn / abandoned Sherman, ORWest Nov 2023target 2028
Onshore wind project 26, Lincoln County
Onshore wind
300 MWWithdrawn / abandoned Lincoln, WYWest Sep 2003target 2006
Solar project Q06, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Aug 2013target 2021
Solar project 783, Power County
Solar
300 MWWithdrawn / abandoned Power, IDWest Apr 2025
Onshore wind project BHBE G12, Campbell County
Onshore wind
300 MWWithdrawn / abandoned Campbell, SDWest Jul 2017target 2023
Page 20 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)