United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in West (non-ISO utilities) — page 20
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project Q233, Maricopa County Solar |
300 MW | Withdrawn / abandoned |
| Solar + storage project C1-59, Converse County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project 572, Jerome County Solar |
300 MW | Withdrawn / abandoned |
| Battery storage project G0938, Benton County Battery storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project C3-124, Juab County Solar + storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project C3-104, Bingham County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project 764, Minidoka County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q385, Pinal County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project Q32, Maricopa County Solar |
300 MW | Withdrawn / abandoned |
| Other project IA-PNM-2014-01, Guadalupe Cty County Other |
300 MW | Withdrawn / abandoned |
| Onshore wind project G0296, Morrow County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project 1049, Utah County Solar |
300 MW | Withdrawn / abandoned |
| Solar + storage project 1220, Klamath County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project GI-2021-21, Pueblo County Solar |
300 MW | Withdrawn / abandoned |
| Solar + storage project Company KE, Churchill County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q15, Pinal County Solar + storage |
300 MW | Withdrawn / abandoned |
| HI300SB Project Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project 1050, Utah County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-2008-2, Huerfano County Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project 498, Sweetwater County Gas |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-2003-1, Morgan County Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project C3-045, Box Elder County Battery storage · PacifiCorp |
300 MW | Withdrawn / abandoned |
| Solar + storage project C3-142, Tooele County Solar + storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project G0298, Columbia County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project CS23-05, Adams County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project GI-2022-12, Pueblo County Solar + storage |
300 MW | Withdrawn / abandoned |
| Battery storage project C2-51, Clark County Battery storage · PacifiCorp |
300 MW | Withdrawn / abandoned |
| Solar + storage project 648, Power County Solar + storage · NextEra Energy Resources Interconnection Holdings, LLC |
300 MW | Withdrawn / abandoned |
| Solar + storage project C3-101, Millard County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project C3-105, Bannock County Solar + storage |
300 MW | Withdrawn / abandoned |
| 300MW Lower Monumental-Starbuck Onshore wind · RES North America |
300 MW | Withdrawn / abandoned |
| Battery storage project G1042, Sherman County Battery storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project 130, Carbon County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project G0632, Grant County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project 925, Platte County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project G0271, Yakima County Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project 222, Converse County Gas · PacifiCorp Energy |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-0810, Meade County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q248, Maricopa County Solar + storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project Q05, Kern County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-0114, Mcintosh County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-0115, Mcintosh County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-2004-9, Elbert County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project 2007-G4 Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project Q525, Mohave County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project G0981, Sherman County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project 26, Lincoln County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project Q06, Maricopa County Solar |
300 MW | Withdrawn / abandoned |
| Solar project 783, Power County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project BHBE G12, Campbell County Onshore wind |
300 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)