United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Geothermal interconnection queue in the USA — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown514,849 MW
Active in queue4,849 MW51 requests
Agreement signed859 MW17 requests
Withdrawn1096,427 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

51 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Geothermal project T2-012, Beaver County
Geothermal
3.6 MWIn study Beaver, UTWest Aug 2025target 2025
Page 2 of 2

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)