United States › Grid › Interconnection queues › Nevada

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Nevada — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8220.9 GW
Active in queue81.5 GW249 requests
Agreement signed20.9 GW82 requests
Withdrawn35588.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

82 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Company IA, Washoe County
Solar
120 MWAgreement signed Washoe, NVWest Dec 2017target 2024
Geothermal project Company LB, Pershing County
Geothermal
115 MWAgreement signed Pershing, NVWest Mar 2021target 2029
Solar project Company 140, Clark County
Solar
100 MWAgreement signed Clark, NVWest Sep 2014target 2025
Solar + storage project Company 174, Clark County
Solar + storage
100 MWAgreement signed Clark, NVWest Mar 2019target 2023
Battery storage project Company HS, Washoe County
Battery storage
100 MWAgreement signed Washoe, NVWest Sep 2017target 2027
Solar project Company HL, Lander County
Solar
100 MWAgreement signed Lander, NVWest Mar 2017target 2023
Battery storage project Company JW, Washoe County
Battery storage
100 MWAgreement signed Washoe, NVWest Sep 2019target 2027
Sunshine Valley Solar 1
Solar + storage
90.0 MWAgreement signed Nye, NVCAISO Apr 2013target 2026
Solar project Company 147, Clark County
Solar
82.3 MWAgreement signed Clark, NVWest Mar 2016target 2025
Solar project Company IH, Pershing County
Solar
80.0 MWAgreement signed Pershing, NVWest Mar 2018target 2021
Solar project Company HP, Lander County
Solar
79.0 MWAgreement signed Lander, NVWest Sep 2017target 2027
Solar project Company HK, Lander County
Solar
70.0 MWAgreement signed Lander, NVWest Sep 2016target 2027
Solar + storage project Company 193, Clark County
Solar + storage
57.0 MWAgreement signed Clark, NVWest Mar 2021target 2026
Battery storage project Company JV, Carson City County
Battery storage
50.0 MWAgreement signed Carson City, NVWest Mar 2019target 2023
Battery storage project Company 155, Clark County
Battery storage
50.0 MWAgreement signed Clark, NVWest Sep 2017target 2023
Geothermal project Company HN, Washoe County
Geothermal
45.0 MWAgreement signed Washoe, NVWest Aug 2017target 2026
Ares Nevada
Battery storage
44.0 MWAgreement signed Nye, NVCAISO Apr 2014target 2027
Geothermal project Company LT, Lander County
Geothermal
40.0 MWAgreement signed Lander, NVWest Sep 2021target 2026
Geothermal project Company KJ, Washoe County
Geothermal
38.5 MWAgreement signed Washoe, NVWest Feb 2020target 2023
Geothermal project Company EV, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Apr 2010target 2026
Geothermal project Company KI, Washoe County
Geothermal
38.5 MWAgreement signed Washoe, NVWest Feb 2020target 2025
Geothermal project Company QK, Lyon County
Geothermal
38.5 MWAgreement signed Lyon, NVWest Sep 2023target 2030
Geothermal project Company KH, Esmeralda County
Geothermal
38.5 MWAgreement signed Esmeralda, NVWest Feb 2020target 2022
Geothermal project Company KG, Eureka County
Geothermal
38.5 MWAgreement signed Eureka, NVWest Feb 2020target 2027
Geothermal project Company KY, Esmeralda County
Geothermal
38.5 MWAgreement signed Esmeralda, NVWest Mar 2021target 2027
Geothermal project Company KZ, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Mar 2021target 2027
Geothermal project Company HU, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Sep 2017target 2023
Battery storage project Company 185, Clark County
Battery storage
30.0 MWAgreement signed Clark, NVWest Sep 2019target 2023
Geothermal project Company LR, Lander County
Geothermal
29.0 MWAgreement signed Lander, NVWest Sep 2021target 2024
Geothermal project Company MM, Esmeralda County
Geothermal
19.8 MWAgreement signed Esmeralda, NVWest Dec 2021target 2025
Geothermal project Company KO, Lyon County
Geothermal
4.8 MWAgreement signed Lyon, NVWest Sep 2020target 2027
Other project Company MN, Lyon County
Other
1.3 MWAgreement signed Lyon, NVWest Dec 2021target 2022
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)