United States › Grid › Interconnection queues › California
OCTARY USA · INTERCONNECTION QUEUESQueue requests in study in California — page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Sagebrush Energy Storage Battery storage |
528 MW | In study |
| Summit Valley Energy Storage Battery storage |
519 MW | In study |
| Lupine Energy Center Battery storage |
518 MW | In study |
| Chronos Energy Storage Battery storage |
517 MW | In study |
| Yacht Rock Battery storage |
514 MW | In study |
| Dove Cove Battery storage |
514 MW | In study |
| Belterra Energy Storage Battery storage |
514 MW | In study |
| Fontus Battery storage |
514 MW | In study |
| Blue Star Solar + storage |
513 MW | In study |
| Rosa Storage Battery storage |
512 MW | In study |
| Bolt Solar + storage |
509 MW | In study |
| Torbino Solar Solar |
507 MW | In study |
| Galicia Storage Battery storage |
506 MW | In study |
| Ambar Energy Storage Battery storage |
505 MW | In study |
| Battery storage project Q108, San Bernardino County Battery storage |
500 MW | In study |
| Battery storage project Q78, Kern County Battery storage |
500 MW | In study |
| Solar + storage project GI-2023-167, Imperial County Solar + storage |
500 MW | In study |
| Solar + storage project Q89, Kern County Solar + storage |
500 MW | In study |
| Hawkins Solar Hybrid Solar + storage |
500 MW | In study |
| Battery storage project Q84, San Bernardino County Battery storage |
500 MW | In study |
| Cantus Solar + storage |
499 MW | In study |
| Corby 2 Battery storage |
476 MW | In study |
| Shoals Energy Storage 2 Battery storage |
461 MW | In study |
| Mineral King Solar Solar + storage |
430 MW | In study |
| Boulder Brush Hybrid Wind + storage |
420 MW | In study |
| Tolenas Battery storage |
417 MW | In study |
| Whiskey Diggings Solar |
414 MW | In study |
| Solstice C Solar + storage |
408 MW | In study |
| Solstice D Solar + storage |
408 MW | In study |
| Maravillosa 1 Solar + storage |
407 MW | In study |
| Lotus Solar 2 Solar + storage |
406 MW | In study |
| Simon Battery storage |
406 MW | In study |
| Coral Reef Battery storage |
406 MW | In study |
| Fleetwood Battery storage |
406 MW | In study |
| Tea Leaf Energy Storage Battery storage |
404 MW | In study |
| Dirac Battery storage |
403 MW | In study |
| Other project SC1Q31, Sacramento County Other |
400 MW | In study |
| Gamay Solar + storage |
400 MW | In study |
| Sequoia Solar + storage |
400 MW | In study |
| Brushy Battery storage |
400 MW | In study |
| Comstock Gas |
398 MW | In study |
| Battery storage project GI-2023-168, Imperial County Battery storage |
387 MW | In study |
| MidBishop Solar + storage |
382 MW | In study |
| Brown Bear Solar + storage |
378 MW | In study |
| Circinus Solar + storage |
371 MW | In study |
| Northeast Central Valley Battery storage |
365 MW | In study |
| Bajada Solar |
353 MW | In study |
| Moonraker Battery storage |
353 MW | In study |
| Zama Battery storage |
353 MW | In study |
| Argos Solar Solar |
352 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)