United States › Grid › Interconnection queues › New Mexico
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in New Mexico, West — page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Me195SB Solar + storage |
195 MW | In study |
| Ve-DL-195SB Solar + storage |
195 MW | In study |
| Onshore wind project IA-PNM-2025-15, Mckinley County Onshore wind |
190 MW | In study |
| Gas project IA-PNM-2025-20, Bernalillo County Gas |
172 MW | In study |
| Sun Lasso Energy Center Battery storage |
153 MW | Agreement signed |
| Battery storage project IA-PNM-2023-18, Valencia County Battery storage |
150 MW | In study |
| Solar + storage project IA-PNM-2023-14, Bernalillo County Solar + storage |
150 MW | In study |
| Battery storage project IA-PNM-2025-13, Valencia County Battery storage |
150 MW | In study |
| Solar + storage project IA-PNM-2021-09, Bernalillo County Solar + storage · NextEra Energy |
150 MW | Agreement signed |
| Huning Energy Solar |
150 MW | In study |
| WA_150SB Project Solar + storage |
150 MW | Paused / redesign |
| Corazon Energy Storage Battery storage |
150 MW | Agreement signed |
| Battery storage project IA-PNM-2021-16, Sandoval County Battery storage · EsVolta Development |
150 MW | Agreement signed |
| Solar + storage project GI-DISIS-2021-04, Otero County Solar + storage |
150 MW | Agreement signed |
| Ve-DL-150SB Solar + storage |
150 MW | In study |
| Globemallow Solar Solar + storage |
150 MW | Agreement signed |
| Battery storage project IA-PNM-2019-19, Bernalillo County Battery storage · PNM ‚Äì Generation |
150 MW | Agreement signed |
| D150S Project Solar + storage |
150 MW | Paused / redesign |
| Solar + storage project IA-PNM-2018-02, Mckinley County Solar + storage · NTUA |
150 MW | Paused / redesign |
| Battery storage project IA-PNM-2020-17, Bernalillo County Battery storage · AES Renewable Holdings |
150 MW | Agreement signed |
| Onshore wind project IA-PNM-2020-01, Guadalupe County Onshore wind |
145 MW | Agreement signed |
| NMRD Data Center IV Solar |
140 MW | Agreement signed |
| LA130S Project Solar + storage |
130 MW | In study |
| Solar + storage project IA-PNM-2019-08, Mckinley County Solar + storage · RWE Solar Dev |
125 MW | Paused / redesign |
| AC120SB Project Solar + storage |
120 MW | Agreement signed |
| Solar project GI-DISIS-2021-01, Harding County Solar |
120 MW | Paused / redesign |
| Battery storage project IA-PNM-2025-12, Cibola County Battery storage |
115 MW | In study |
| Battery storage project IA-PNM-2024-01, Roosevelt County Battery storage |
100 MW | In study |
| CO100SB Project Solar + storage |
100 MW | Agreement signed |
| Battery storage project IA-PNM-2019-18, Bernalillo County Battery storage |
100 MW | Paused / redesign |
| VE100S Project Solar + storage |
100 MW | Agreement signed |
| Battery storage project IA-PNM-2025-11, Valencia County Battery storage |
100 MW | In study |
| Battery storage project IA-PNM-2022-11, Bernalillo County Battery storage |
100 MW | In study |
| Zinnia Storage Battery storage |
100 MW | Agreement signed |
| AN100S Solar |
100 MW | Agreement signed |
| Solar + storage project IA-PNM-2020-07, San Juan County Solar + storage |
100 MW | In study |
| Solar + storage project IA-PNM-2022-03, Santa Fe County Solar + storage |
100 MW | In study |
| Solar + storage project IA-PNM-2020-21, Valencia County Solar + storage |
100 MW | Agreement signed |
| Solar project IA-PNM-2018-03, San Juan County Solar · DESRI Rockmont Development |
100 MW | Paused / redesign |
| Solar + storage project IA-PNM-2019-05, Santa Fe County Solar + storage |
96.0 MW | Agreement signed |
| Solar project IA-PNM-2017-15, San Juan County Solar |
95.6 MW | Agreement signed |
| Solar + storage project IA-PNM-2020-06, Mckinley County Solar + storage |
90.0 MW | In study |
| Ambrosia Solar Solar + storage · Ambrosia Solar |
90.0 MW | Paused / redesign |
| Wildcat Solar Power Plant Solar + storage |
90.0 MW | Paused / redesign |
| Gas project IA-PNM-2020-05, San Juan County Gas · PNM ‚Äì Generation |
80.0 MW | Agreement signed |
| Onshore wind project IA-PNM-2019-12, Torrance County Onshore wind |
80.0 MW | In study |
| Gas project IA-PNM-2014-02, San Juan County Gas |
80.0 MW | Agreement signed |
| Iris Del Sol Solar + storage |
76.0 MW | Agreement signed |
| VS75SB Solar + storage |
75.0 MW | Paused / redesign |
| Solar + storage project IA-PNM-2017-11, Torrance County Solar + storage |
74.9 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)