OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in SPP (Southwest Power Pool) (2017 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6611.8 GW
Active in queue11.8 GW66 requests
Agreement signed11.4 GW64 requests
Withdrawn16232.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

66 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2017-214, Ward County
Onshore wind
100 MWAgreement signed Ward, NDSPP Nov 2017target 2030
Solar project GEN-2017-023, Choctaw County
Solar
85.0 MWAgreement signed Choctaw, OKSPP May 2017target 2026
Onshore wind project GEN-2017-105, Burt County
Onshore wind
75.0 MWAgreement signed Burt, NESPP Jul 2017target 2026
Solar project GEN-2017-057, Caddo Parish County
Solar
72.5 MWAgreement signed Caddo Parish, LASPP May 20172025
Solar project GEN-2017-231, Franklin County
Solar
72.5 MWAgreement signed Franklin, ARSPP Nov 2017target 2027
Solar project GEN-2017-230, Lincoln County
Solar
72.5 MWAgreement signed Lincoln, OKSPP Nov 2017target 2027
Solar project GEN-2017-074, Mayes County
Solar
72.5 MWAgreement signed Mayes, OKSPP May 20172025
Solar project GEN-2017-073, Mayes County
Solar
72.5 MWAgreement signed Mayes, OKSPP May 20172025
Solar project GEN-2017-022, Wilson County
Solar
65.0 MWAgreement signed Wilson, KSSPP May 2017target 2027
Solar project GEN-2017-072, Payne County
Solar
52.2 MWAgreement signed Payne, OKSPP May 20172025
Solar project GEN-2017-232, Bryan County
Solar
52.2 MWAgreement signed Bryan, OKSPP Nov 2017target 2026
Battery storage project GEN-2017-178, Garfield County
Battery storage
52.0 MWAgreement signed Garfield, OKSPP Nov 20172025
Solar project GEN-2017-173, Comanche County
Solar
50.0 MWAgreement signed Comanche, OKSPP Nov 2017target 2027
Solar project GEN-2017-172, Comanche County
Solar
50.0 MWAgreement signed Comanche, OKSPP Nov 2017target 2027
Battery storage project GEN-2017-117, Canadian County
Battery storage
19.8 MWPaused / redesign Canadian, OKSPP Nov 2017target 2029
Battery storage project GEN-2017-198, Douglas County
Battery storage
11.6 MWAgreement signed Douglas, NESPP Nov 2017target 2027
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)