Requests shown13866.9 GW
Active in queue66.9 GW138 requests
Agreement signed35.4 GW68 requests
Withdrawn22082.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

138 requests Β· page 2 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Dos Palmas
Battery storage
411 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2031
Hidalgo Energy Storage
Battery storage
408 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2033
Clarkson
Solar + storage
408 MWAgreement signed Fresno, CACAISO Apr 2021target 2029
Lotus Solar 2
Solar + storage
406 MWIn study Madera, CACAISO Apr 2021target 2030
Simon
Battery storage
406 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Gabriel Storage
Battery storage
406 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2033
Trolley
Battery storage
406 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2031
Coral Reef
Battery storage
406 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Fleetwood
Battery storage
406 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Marici
Battery storage
406 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2031
Dirac
Battery storage
403 MWIn study San Bernardino, CACAISO Apr 2021target 2031
Brushy
Battery storage
400 MWIn study Solano, CACAISO Apr 2021target 2031
Golden Flats
Battery storage
365 MWAgreement signed Stanislaus, CACAISO Apr 2021target 2031
Espresso
Battery storage
365 MWAgreement signed Alameda, CACAISO Apr 2021target 2031
Northeast Central Valley
Battery storage
365 MWIn study San Joaquin, CACAISO Apr 2021target 2031
Allegheny Energy Storage
Battery storage
353 MWAgreement signed Contra Costa, CACAISO Apr 2021target 2032
Dandelion Hybrid Solar
Solar + storage
334 MWIn study Nye, NVCAISO Apr 2021target 2027
Harquahala Sunrise 2
Solar + storage
330 MWIn study Maricopa, AZCAISO Apr 2021target 2026
Ariella Solar
Solar + storage
327 MWAgreement signed Tulare, CACAISO Apr 2021target 2030
Spikes Peak Solar
Solar + storage
318 MWAgreement signed Merced, CACAISO Apr 2021target 2029
Cargo Storage
Battery storage
313 MWIn study San Diego, CACAISO Apr 2021target 2036
Haven Storage
Battery storage
313 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2031
Bell Bluff Storage
Battery storage
313 MWIn study San Diego, CACAISO Apr 2021target 2035
Harmony Storage 2
Battery storage
308 MWIn study Contra Costa, CACAISO Apr 2021target 2031
Juniper Storage
Solar + storage
307 MWIn study Los Angeles, CACAISO Apr 2021target 2033
Gnarly Osage
Battery storage
304 MWIn study San Diego, CACAISO Apr 2021target 2027
Elion Energy Storage
Battery storage
302 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2034
Tyrell Energy Storage
Battery storage
302 MWAgreement signed Orange, CACAISO Apr 2021target 2032
Tabla Energy Storage
Battery storage
302 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2032
Electron
Battery storage
300 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2033
Carmine
Battery storage
292 MWIn study Riverside, CACAISO Apr 2021target 2031
Pathfinder Storage
Battery storage
268 MWAgreement signed San Joaquin, CACAISO Apr 2021target 2031
J90 Energy Storage
Battery storage
261 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2033
Delamar Energy Storage 2
Battery storage
256 MWIn study Clark, NVCAISO Apr 2021target 2027
Commerce Energy Storage 3
Battery storage
256 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2031
Almande Energy Storage
Battery storage
256 MWIn study Merced, CACAISO Apr 2021target 2030
Sherman Energy Storage
Battery storage
256 MWIn study Contra Costa, CACAISO Apr 2021target 2031
Gateway Energy Storage 2
Battery storage
256 MWIn study San Diego, CACAISO Apr 2021target 2035
Sandbar Energy Storage
Battery storage
256 MWIn study San Diego, CACAISO Apr 2021target 2030
Ciervo Mountain Hybrid
Solar + storage
255 MWAgreement signed Fresno, CACAISO Apr 2021target 2029
Sandrift Storage 1
Battery storage
255 MWAgreement signed Riverside, CACAISO Apr 2021target 2030
Sandrift Storage 2
Battery storage
255 MWAgreement signed Riverside, CACAISO Apr 2021target 2031
Greenwood Energy Storage
Battery storage
252 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2032
Zorin Storage
Battery storage
252 MWAgreement signed Alameda, CACAISO Apr 2021target 2034
Baylands Battery
Battery storage
250 MWAgreement signed San Mateo, CACAISO Apr 2021target 2030
Allium Hybrid
Solar + storage
225 MWAgreement signed San Benito, CACAISO Apr 2021target 2030
Dorian Storage
Battery storage
214 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2034
Zeus BESS
Battery storage
214 MWAgreement signed San Joaquin, CACAISO Apr 2021target 2031
Weston Storage
Battery storage
214 MWIn study San Bernardino, CACAISO Apr 2021target 2031
Frigatebird Storage
Battery storage
214 MWIn study San Diego, CACAISO Apr 2021target 2035

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)