| Project | Capacity | Status |
|---|---|---|
| Dos Palmas Battery storage |
411 MW | Agreement signed |
| Hidalgo Energy Storage Battery storage |
408 MW | Agreement signed |
| Clarkson Solar + storage |
408 MW | Agreement signed |
| Lotus Solar 2 Solar + storage |
406 MW | In study |
| Simon Battery storage |
406 MW | In study |
| Gabriel Storage Battery storage |
406 MW | Agreement signed |
| Trolley Battery storage |
406 MW | Agreement signed |
| Coral Reef Battery storage |
406 MW | In study |
| Fleetwood Battery storage |
406 MW | In study |
| Marici Battery storage |
406 MW | Agreement signed |
| Dirac Battery storage |
403 MW | In study |
| Brushy Battery storage |
400 MW | In study |
| Golden Flats Battery storage |
365 MW | Agreement signed |
| Espresso Battery storage |
365 MW | Agreement signed |
| Northeast Central Valley Battery storage |
365 MW | In study |
| Allegheny Energy Storage Battery storage |
353 MW | Agreement signed |
| Dandelion Hybrid Solar Solar + storage |
334 MW | In study |
| Harquahala Sunrise 2 Solar + storage |
330 MW | In study |
| Ariella Solar Solar + storage |
327 MW | Agreement signed |
| Spikes Peak Solar Solar + storage |
318 MW | Agreement signed |
| Cargo Storage Battery storage |
313 MW | In study |
| Haven Storage Battery storage |
313 MW | Agreement signed |
| Bell Bluff Storage Battery storage |
313 MW | In study |
| Harmony Storage 2 Battery storage |
308 MW | In study |
| Juniper Storage Solar + storage |
307 MW | In study |
| Gnarly Osage Battery storage |
304 MW | In study |
| Elion Energy Storage Battery storage |
302 MW | Agreement signed |
| Tyrell Energy Storage Battery storage |
302 MW | Agreement signed |
| Tabla Energy Storage Battery storage |
302 MW | Agreement signed |
| Electron Battery storage |
300 MW | Agreement signed |
| Carmine Battery storage |
292 MW | In study |
| Pathfinder Storage Battery storage |
268 MW | Agreement signed |
| J90 Energy Storage Battery storage |
261 MW | Agreement signed |
| Delamar Energy Storage 2 Battery storage |
256 MW | In study |
| Commerce Energy Storage 3 Battery storage |
256 MW | Agreement signed |
| Almande Energy Storage Battery storage |
256 MW | In study |
| Sherman Energy Storage Battery storage |
256 MW | In study |
| Gateway Energy Storage 2 Battery storage |
256 MW | In study |
| Sandbar Energy Storage Battery storage |
256 MW | In study |
| Ciervo Mountain Hybrid Solar + storage |
255 MW | Agreement signed |
| Sandrift Storage 1 Battery storage |
255 MW | Agreement signed |
| Sandrift Storage 2 Battery storage |
255 MW | Agreement signed |
| Greenwood Energy Storage Battery storage |
252 MW | Agreement signed |
| Zorin Storage Battery storage |
252 MW | Agreement signed |
| Baylands Battery Battery storage |
250 MW | Agreement signed |
| Allium Hybrid Solar + storage |
225 MW | Agreement signed |
| Dorian Storage Battery storage |
214 MW | Agreement signed |
| Zeus BESS Battery storage |
214 MW | Agreement signed |
| Weston Storage Battery storage |
214 MW | In study |
| Frigatebird Storage Battery storage |
214 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)228 Β· 68.8 GW
- CAISO (California)138 Β· 66.9 GW
- ERCOT (Texas)207 Β· 39.5 GW
- MISO (Midcontinent)136 Β· 23.7 GW
- Southeast (non-ISO utilities)63 Β· 12.7 GW
- SPP (Southwest Power Pool)44 Β· 9,029 MW
- ISO-NE (New England)20 Β· 3,998 MW
- PJM (Mid-Atlantic, Midwest)49 Β· 2,072 MW
- NYISO (New York)11 Β· 991 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)