United States › Grid › Interconnection queues › Pennsylvania

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Pennsylvania — page 15

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,354164.3 GW
Active in queue12.5 GW231 requests
Agreement signed2,306 MW58 requests
Withdrawn1,354164.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,354 requests · page 15 of 28
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AG2-652, Carbon County
Solar
20.0 MWWithdrawn / abandoned Carbon, PAPJM Mar 2021target 2024
Evergreene Energy
Gas
20.0 MWWithdrawn / abandoned Greene, PAPJM Oct 2017target 2022
Solar project AG1-227, Schuylkill County
Solar
20.0 MWWithdrawn / abandoned Schuylkill, PAPJM Sep 2020target 2023
Solar project AH1-230, Tioga County
Solar
20.0 MWWithdrawn / abandoned Tioga, PAPJM Sep 2021target 2025
Solar + storage project AG1-278, Luzerne County
Solar + storage · LU-Tank LLC
20.0 MWWithdrawn / abandoned Luzerne, PAPJM Sep 2020target 2022
Solar project Y2-061, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Aug 2012target 2014
Solar project W1-043, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2010target 2011
Battery storage project V3-057, Lebanon County
Battery storage
20.0 MWWithdrawn / abandoned Lebanon, PAPJM Oct 2009target 2011
Solar project AF2-170, Erie County
Solar
20.0 MWWithdrawn / abandoned Erie, PAPJM Mar 2020target 2022
Solar project AG1-280, Blair County
Solar
20.0 MWWithdrawn / abandoned Blair, PAPJM Sep 2020target 2022
McKean Solar 2 - Energy Storage
Battery storage · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PAPJM Feb 2025target 2024
Solar project AG2-594, Columbia County
Solar · North Corners Energy, LLC
20.0 MWWithdrawn / abandoned Columbia, PAPJM Mar 2021target 2024
Solar + storage project AG2-593, Columbia County
Solar + storage
20.0 MWWithdrawn / abandoned Columbia, PAPJM Mar 2021target 2024
Big Bell Solar
Solar
20.0 MWWithdrawn / abandoned Crawford, PAPJM Aug 2019target 2023
Dover Solar and BESS
Battery storage
20.0 MWWithdrawn / abandoned York, PAPJM Jul 2020target 2026
Battery storage project AG2-653, Carbon County
Battery storage
20.0 MWWithdrawn / abandoned Carbon, PAPJM Mar 2021target 2024
Nittany Solar
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2018target 2022
Solar project AF2-333, Montour County
Solar
20.0 MWWithdrawn / abandoned Montour, PAPJM Mar 2020target 2023
Ellistown Solar & BESS
Solar + storage
20.0 MWWithdrawn / abandoned Bradford, PAPJM Sep 2019target 2027
Solar project AH1-005, Bradford County
Solar · Franklin Energy, LLC
20.0 MWWithdrawn / abandoned Bradford, PAPJM Jan 2025target 2025
Solar project AE1-165, Cambria County
Solar
20.0 MWWithdrawn / abandoned Cambria, PAPJM Sep 2018target 2021
Solar project W1-052, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2010target 2011
Solar project W3-069, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Sep 2010target 2012
Solar project W1-013, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Feb 2010target 2011
Solar project AF1-242, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2019target 2022
Solar project V3-031, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Aug 2009target 2010
Solar project AH1-488, Mercer County
Solar
20.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2021target 2024
Wilson Battery Storage
Battery storage
20.0 MWWithdrawn / abandoned Allegheny, PAPJM Oct 2015target 2019
Solar project W2-093, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Jul 2010target 2013
South Troy - North Towanda 34.5 kV
Solar · Franklin Energy, LLC
20.0 MWWithdrawn / abandoned Bradford, PANYISO Sep 2025
Maysville Solar 2
Solar · PD Solar 11 LLC
20.0 MWWithdrawn / abandoned Mercer, PAPJM Jan 2025target 2024
Solar project W1-014, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Feb 2010target 2011
Other project Y2-011, Allegheny County
Other
20.0 MWWithdrawn / abandoned Allegheny, PAPJM May 2012target 2015
Solar project X3-062, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Oct 2011target 2012
Battery storage project Y3-104, Luzerne County
Battery storage
20.0 MWWithdrawn / abandoned Luzerne, PAPJM Apr 2013target 2015
Great Cove Solar
Solar
20.0 MWWithdrawn / abandoned Fulton, PAPJM Feb 2020target 2027
Solar project AH1-406, Northumberland County
Solar
20.0 MWWithdrawn / abandoned Northumberland, PAPJM Sep 2021target 2024
Solar project W3-064, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2010target 2011
Solar project W2-092, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Jul 2010target 2013
Solar + storage project AG2-415, Potter County
Solar + storage
20.0 MWWithdrawn / abandoned Potter, PAPJM Mar 2021target 2025
Solar project W3-008, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Aug 2010target 2012
Solar project X4-009, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Nov 2011target 2014
Solar project AF2-422, Luzerne County
Solar
20.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2020target 2022
Solar project X3-034, Washington County
Solar
20.0 MWWithdrawn / abandoned Washington, PAPJM Aug 2011target 2012
Solar project W2-097, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Jul 2010target 2012
Solar project W3-072, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2010target 2012
Solar project AF2-334, Montour County
Solar
20.0 MWWithdrawn / abandoned Montour, PAPJM Mar 2020target 2023
ASD Warner PA2 Solar LLC
Solar · ASD Warner PA2 Solar LLC
20.0 MWWithdrawn / abandoned Tioga, PAPJM Aug 2021target 2023
Solar project AG1-395, Clearfield County
Solar
20.0 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2020target 2022
Gas project AH1-708, Adams County
Gas · Hunterstown Generation, LLC
20.0 MWWithdrawn / abandoned Adams, PAPJM target 2025
Page 15 of 28

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)