Queue requests in study in Southeast (non-ISO utilities) — page 15

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown815118.5 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

815 requests · page 15 of 17
ProjectCapacityStatusLocationRegionQueuedOnline
Nuclear project 637, Hamilton County
Nuclear
24.0 MWIn study Hamilton, TNSoutheast Aug 2024target 2027
Hydro project 655, Hamilton County
Hydro
24.0 MWIn study Hamilton, TNSoutheast Sep 2024target 2028
Hydro project 654, Hamilton County
Hydro
24.0 MWIn study Hamilton, TNSoutheast Sep 2024target 2028
Gas project 20211104002, Calhoun County
Gas · DESC - Generation
23.0 MWIn study Calhoun, SCSoutheast target 2022
Solar project LGE-GIS-2024-004, Mercer County
Solar
22.0 MWIn study Mercer, KYSoutheast Apr 2024target 2026
Other project 977788, Columbus County
Other
22.0 MWIn study Columbus, NCSoutheast Jun 2025
Coal project GI-40, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Coal project GI-39, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Gas project 199, Anderson County
Gas
20.0 MWIn study Anderson, SCSoutheast Jun 2023
Battery storage project 120, Polk County
Battery storage
20.0 MWIn study Polk, FLSoutheast May 2025target 2027
Nuclear project 25-IC-1303, Burke County
Nuclear
20.0 MWIn study Burke, GASoutheast Mar 2025target 2027
Gas project 978030, Anderson County
Gas
20.0 MWIn study Anderson, SCSoutheast Apr 2025
Gas project 900845, Buncombe County
Gas · Duke Energy Progress, LLC
19.9 MWIn study Buncombe, NCSoutheast Jun 2023target 2025
Solar project 977885, Greenwood County
Solar
19.9 MWIn study Greenwood, SCSoutheast Jun 2025
Gas project 900843, Buncombe County
Gas · Duke Energy Progress, LLC
19.9 MWIn study Buncombe, NCSoutheast Jun 2023target 2025
Solar project 977884, Chester County
Solar
19.9 MWIn study Chester, SCSoutheast Jun 2025
Solar project 123, Polk County
Solar
19.5 MWIn study Polk, FLSoutheast May 2025target 2027
Gas project LGE-CS2025-011, Trimble County
Gas
19.0 MWIn study Trimble, KYSoutheast Dec 2025target 2029
Gas project LGE-CS2025-012, Trimble County
Gas
19.0 MWIn study Trimble, KYSoutheast Dec 2025target 2030
Hydro project 476, Lyon County
Hydro
18.0 MWIn study Lyon, KYSoutheast Apr 2021target 2027
Gas project 196, Anderson County
Gas
18.0 MWIn study Anderson, SCSoutheast Jun 2023
Gas project 198, Anderson County
Gas
18.0 MWIn study Anderson, SCSoutheast Jun 2023
Gas project 197, Anderson County
Gas
18.0 MWIn study Anderson, SCSoutheast Jun 2023
Gas project 195, Anderson County
Gas
18.0 MWIn study Anderson, SCSoutheast Jun 2023
Gas project LGE-CS2025-008, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Gas project LGE-CS2025-006, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Gas project PP00016, New Hanover County
Gas
17.0 MWIn study New Hanover, NCSoutheast Apr 2025target 2026
Gas project LGE-CS2025-005, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Gas project LGE-CS2025-007, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Coal project GI-41, Randolph County
Coal
17.0 MWIn study Randolph, MOSoutheast Oct 2009target 2012
Gas project 957712, New Hanover County
Gas · Duke Energy Progress LLC
17.0 MWIn study New Hanover, NCSoutheast Jun 2024
Gas project LGE-CS2025-010, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Gas project LGE-CS2025-009, Trimble County
Gas
17.0 MWIn study Trimble, KYSoutheast Dec 2025target 2026
Nuclear project 25-IC-1304, Burke County
Nuclear
16.0 MWIn study Burke, GASoutheast Mar 2025target 2027
Nuclear project 25-IC-1297, Burke County
Nuclear
15.0 MWIn study Burke, GASoutheast Mar 2025target 2029
Nuclear project 25-IC-1299, Burke County
Nuclear
15.0 MWIn study Burke, GASoutheast Mar 2025target 2028
Nuclear project 25-IC-1308, Houston County
Nuclear
15.0 MWIn study Houston, ALSoutheast Apr 2025target 2029
Nuclear project 25-IC-1306, Houston County
Nuclear
15.0 MWIn study Houston, ALSoutheast Apr 2025target 2030
Gas project 25-IC-1344, Mobile County
Gas
14.0 MWIn study Mobile, ALSoutheast Apr 2025target 2028
Gas project 25-IC-1289, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2028
Gas project 25-IC-1287, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2027
Gas project 25-IC-1288, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2028
Gas project 25-IC-1290, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2029
Gas project 25-IC-1292, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2031
Gas project 25-IC-1291, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2030
Gas project 25-IC-1293, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2032
Gas project 25-IC-1294, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2033
Gas project 20211118001, Berkeley County
Gas · DESC - Generation
13.4 MWIn study Berkeley, SCSoutheast target 2024
Other project FC100000, Pasco County
Other · Masked
13.1 MWIn study Pasco, FLSoutheast Dec 2024target 2026
Nuclear project 957251, Brunswick County
Nuclear · Duke Energy Progress LLC
13.0 MWIn study Brunswick, NCSoutheast Jun 2024
Page 15 of 17

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)