🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in PJM (Mid-Atlantic, Midwest) — page 15

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown905105.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

905 requests · page 15 of 19
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AG2-356, Bradford County
Solar · Robin Solar LLC
20.0 MWIn study Bradford, PAPJM Jan 2025target 2023
Solar project AH1-072, Dickenson County
Solar · Bold Camp CF Solar, LLC
20.0 MWIn study Dickenson, VAPJM Mar 2025target 2024
Crossroads Solar I
Solar · Crossroads Solar I, LLC
20.0 MWIn study Morrow, OHPJM Apr 2025target 2024
Solar project AI2-175, Westmoreland County
Solar
20.0 MWIn study Westmoreland, VAPJM Feb 2023target 2025
Horsepen Creek Solar I
Solar · Horsepen Creek Solar, LLC
20.0 MWIn study Goochland, VAPJM Mar 2025target 2024
Solar + storage project AI2-436, Clearfield County
Solar + storage
20.0 MWIn study Clearfield, PAPJM Mar 2023target 2026
Solar project AH1-280, Amelia County
Solar · Amelia Energy Facility, LLC
20.0 MWIn study Amelia, VAPJM Feb 2025target 2023
Dover Solar
Solar
20.0 MWPaused / redesign York, PAPJM Jul 2019target 2026
Gas project AH1-679, Hanover County
Gas · Doswell Limited Partnership
20.0 MWIn study Hanover, VAPJM Apr 2025
HU-Logging
Solar
20.0 MWPaused / redesign Huntingdon, PAPJM Feb 2019target 2024
Charles County Solar I
Solar
20.0 MWPaused / redesign Charles, MDPJM Apr 2019target 2028
SunEast Hooversville Solar
Solar
20.0 MWPaused / redesign Somerset, PAPJM Oct 2019target 2026
Solar project AH2-399, Rockingham County
Solar
20.0 MWIn study Rockingham, VAPJM Mar 2022target 2026
Confer Solar I
Solar
20.0 MWPaused / redesign Centre, PAPJM Oct 2018target 2026
Solar project AH1-071, Powhatan County
Solar · Virginia Electric and Power Company
20.0 MWIn study Powhatan, VAPJM Feb 2025target 2023
Solar project AH2-046, Mecklenburg County
Solar
20.0 MWIn study Mecklenburg, VAPJM Dec 2021target 2025
Solar project AH2-187, Clarion County
Solar
20.0 MWIn study Clarion, PAPJM Mar 2022target 2025
Solar + storage project AI1-214, Centre County
Solar + storage
20.0 MWIn study Centre, PAPJM Sep 2022target 2024
Solar + storage project AI2-441, Luzerne County
Solar + storage
20.0 MWIn study Luzerne, PAPJM Mar 2023target 2027
Railroad Energy Center
Battery storage · Railroad Energy Center, LLC
20.0 MWIn study Prince William, VAPJM Feb 2025target 2022
Solar project AI2-437, Warren County
Solar
20.0 MWIn study Warren, NJPJM Mar 2023target 2024
SunEast Hooversville Solar
Solar
20.0 MWPaused / redesign Somerset, PAPJM Sep 2019target 2026
Solar project AH2-400, Rockingham County
Solar
20.0 MWIn study Rockingham, VAPJM Mar 2022target 2026
Solar + storage project AI1-215, Centre County
Solar + storage
20.0 MWIn study Centre, PAPJM Sep 2022target 2024
Solar project AH1-073, Dickenson County
Solar · Bold Camp CF Solar, LLC
20.0 MWIn study Dickenson, VAPJM Feb 2025target 2024
Solar + storage project AI2-440, Centre County
Solar + storage
20.0 MWIn study Centre, PAPJM Mar 2023target 2027
Solar project AH2-028A, Pickaway County
Solar
20.0 MWIn study Pickaway, OHPJM Nov 2021target 2025
Alexandria
Other · Reworld REC LLC
20.0 MWIn study Arlington, VAPJM Feb 2025target 2020
Charles County Solar II
Solar
20.0 MWPaused / redesign Charles, MDPJM Apr 2019target 2027
Solar project AG2-447, New Castle County
Solar · Freepoint Solar LLC
20.0 MWIn study New Castle, DEPJM Feb 2025target 2024
Solar + storage project AI2-434, Lycoming County
Solar + storage
20.0 MWIn study Lycoming, PAPJM Mar 2023target 2026
Solar project AH2-100, Prince Edward County
Solar
20.0 MWIn study Prince Edward, VAPJM Jan 2022target 2023
Jakes Hollow Solar
Solar
20.0 MWPaused / redesign Elk, PAPJM Sep 2019target 2027
Bethlehem Energy Center
Battery storage · Bethlehem Energy Center, LLC
20.0 MWIn study Prince William, VAPJM Feb 2025target 2022
Solar project AH1-138, City Of Williamsburg County
Solar · Virginia Electric and Power Company
20.0 MWIn study City Of Williamsburg, VAPJM Feb 2025target 2022
Solar project AG2-561, Indiana County
Solar · Chestnut Solar LLC
20.0 MWIn study Indiana, PAPJM Mar 2025target 2023
Solar project AG2-236, Lawrence County
Solar · Harlansburg PV I, LLC
20.0 MWIn study Lawrence, PAPJM Feb 2025target 2024
McVille Solar
Solar · IMG Solar LLC
19.9 MWIn study Armstrong, PAPJM Mar 2025target 2023
Solar project AI1-143, Armstrong County
Solar
19.9 MWIn study Armstrong, PAPJM Sep 2022target 2025
Solar + storage project AI1-152, Northampton County
Solar + storage
19.9 MWIn study Northampton, PAPJM Sep 2022target 2027
Solar project AG2-016, Ocean County
Solar · Lacey Holding / Ocean View Acres
19.8 MWIn study Ocean, NJPJM Mar 2025target 2021
Cedar Creek Solar
Solar
19.8 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Solar project AH2-163, Armstrong County
Solar
19.8 MWIn study Armstrong, PAPJM Mar 2022target 2026
Norwegian Solar
Solar
19.8 MWPaused / redesign Northumberland, PAPJM Apr 2020target 2024
Cedar Creek Solar
Solar
19.8 MWPaused / redesign New Castle, DEPJM Oct 2016target 2027
Solar project AI1-076, Delaware County
Solar
19.8 MWIn study Delaware, PAPJM Jul 2022target 2024
Solar project AH1-397, King And Queen County
Solar · Ameresco Inc
19.7 MWIn study King And Queen, VAPJM Feb 2025target 2023
Solar project AG2-625, Warren County
Solar · Chamberlain West Solar Farm LLC
19.6 MWIn study Warren, NJPJM Feb 2025target 2021
Solar project AH2-096, Dorchester County
Solar
19.5 MWIn study Dorchester, MDPJM Feb 2022target 2023
Solar project AH1-033, Currituck County
Solar · Sligo Solar, LLC
19.5 MWIn study Currituck, NCPJM Feb 2025target 2024
Page 15 of 19

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)