United States › Grid › Interconnection queues › Pennsylvania
SOLAR · PJMSolar project AI1-076, Delaware County
Solar project AI1-076, Delaware County is a 19.8 MW solar request in interconnection study in the PJM interconnection queue, in Delaware County, Pennsylvania, connecting to PECO.
- PlanningQueued Jul 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-076
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PECO
- Connection point (POI)
- TBD 13.2 kV
- Location
- Delaware County, Pennsylvania
- Technology
- Solar: 19.8 MW
- Total requested
- 19.8 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 11 July 2022
- Proposed online date
- June 2024
Location
Marker shows the centre of Delaware County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Delaware County
- Springfield CSG 1Solar · 3.9 MW · suspended
- Liberty (Eddy)Gas · 521 MW · built
- Phillips Island CT1, CT2, CT3, and ST4Gas · 67.0 MW · built
- Liberty ElectricGas · 65.5 MW · built
- Liberty ElectricGas · 35.0 MW · built
- Phillips Island CT1, CT2,CT3 & ST4Gas · 35.0 MW · built
- JerichoGas · 29.0 MW · built
- Kimberly ClarkOther · 20.0 MW · built
- LibertyGas · 20.0 MW · built
- Phillips Island CT1, CT2, CT3, CT4Gas · 10.0 MW · built
- Sunoil Gen UnitGas · 8.0 MW · built
- EddystoneCoal · 7.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem