Solar project AI1-076, Delaware County

Solar project AI1-076, Delaware County is a 19.8 MW solar request in interconnection study in the PJM interconnection queue, in Delaware County, Pennsylvania, connecting to PECO.

Queue statusIn planning
  1. PlanningQueued Jul 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI1-076
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PECO
Connection point (POI)
TBD 13.2 kV
Location
Delaware County, Pennsylvania
Technology
Solar: 19.8 MW
Total requested
19.8 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
11 July 2022
Proposed online date
June 2024

Location

Marker shows the centre of Delaware County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Delaware County