🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Virginia — page 14

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown86886.8 GW
Active in queue30.3 GW287 requests
Agreement signed7,318 MW72 requests
Withdrawn86886.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

868 requests · page 14 of 18
ProjectCapacityStatusLocationRegionQueuedOnline
Four Rivers NUG CC-1
Gas
20.0 MWWithdrawn / abandoned Hanover, VAPJM Apr 2012target 2016
Solar project AH1-175, Henry County
Solar
20.0 MWWithdrawn / abandoned Henry, VAPJM Aug 2021target 2022
Solar + storage project AF2-327, Sussex County
Solar + storage
20.0 MWWithdrawn / abandoned Sussex, VAPJM Mar 2020target 2023
Solar + storage project AG2-102, Accomack County
Solar + storage
20.0 MWWithdrawn / abandoned Accomack, VAPJM Jan 2021target 2024
Battery storage project AG2-203, City Of Lynchburg County
Battery storage
20.0 MWWithdrawn / abandoned City Of Lynchburg, VAPJM Mar 2021target 2022
Solar project AH1-171, Goochland County
Solar
20.0 MWWithdrawn / abandoned Goochland, VAPJM Aug 2021target 2024
Solar project AE1-180, Culpeper County
Solar
20.0 MWWithdrawn / abandoned Culpeper, VAPJM Sep 2018target 2020
Solar project AD1-158, City Of Chesapeake County
Solar
20.0 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Sep 2017target 2019
Solar project AI2-034, Sussex County
Solar
20.0 MWWithdrawn / abandoned Sussex, VAPJM Jan 2023target 2024
Other project S99, Prince William County
Other
20.0 MWWithdrawn / abandoned Prince William, VAPJM Jul 2007target 2013
Sweetspire
Solar
20.0 MWWithdrawn / abandoned Hanover, VAPJM Mar 2017target 2020
Solar project V4-053, Clarke County
Solar
20.0 MWWithdrawn / abandoned Clarke, VAPJM Dec 2009target 2011
Battery storage project AH1-126, Prince William County
Battery storage
20.0 MWWithdrawn / abandoned Prince William, VAPJM Aug 2021target 2022
Leatherwood
Solar
20.0 MWWithdrawn / abandoned Henry, VAPJM Oct 2016target 2021
Battery storage project AG2-229, Floyd County
Battery storage
20.0 MWWithdrawn / abandoned Floyd, VAPJM Mar 2021target 2024
Culpeper North
Solar
20.0 MWWithdrawn / abandoned Culpeper, VAPJM Mar 2017target 2021
Solar project W1-008, Accomack County
Solar
20.0 MWWithdrawn / abandoned Accomack, VAPJM Feb 2010target 2016
Solar project V3-061, Northampton County
Solar
20.0 MWWithdrawn / abandoned Northampton, VAPJM Oct 2009target 2011
Solar project AG2-410, Southampton County
Solar
20.0 MWWithdrawn / abandoned Southampton, VAPJM Mar 2021target 2023
Bradley Ridge Solar
Solar
20.0 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2019target 2025
Solar project AG2-607, King And Queen County
Solar · Cauthornville PV I, LLC
20.0 MWWithdrawn / abandoned King And Queen, VAPJM Mar 2021target 2023
Solar project AE2-108, Hanover County
Solar
20.0 MWWithdrawn / abandoned Hanover, VAPJM Feb 2019target 2020
Solar project AG1-073, Caroline County
Solar
20.0 MWWithdrawn / abandoned Caroline, VAPJM Jul 2020target 2022
Solar project AG1-175, Surry County
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM Sep 2020target 2021
Ex-Umphlette LLC
Solar
20.0 MWWithdrawn / abandoned Essex, VAPJM Sep 2020target 2023
Battery storage project AG1-155, Botetourt County
Battery storage
20.0 MWWithdrawn / abandoned Botetourt, VAPJM Sep 2020target 2023
Gas project X3-032, Prince George County
Gas
20.0 MWWithdrawn / abandoned Prince George, VAPJM Aug 2011target 2015
NW-Rocky Ford Solar
Solar · NW-Rocky Ford LLC
20.0 MWWithdrawn / abandoned Nottoway, VAPJM Sep 2020target 2021
Summersweet Energy Center, LLC
Battery storage · Summersweet Energy Center, LLC
20.0 MWWithdrawn / abandoned Fauquier, VAPJM Feb 2025target 2023
Solar project AF1-016, City Of Suffolk County
Solar
20.0 MWWithdrawn / abandoned City Of Suffolk, VAPJM Apr 2019target 2021
Mantura
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM Feb 2019target 2022
Solar project AG2-667, Surry County
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM Mar 2021target 2023
Solar project AH2-186, King William County
Solar
20.0 MWWithdrawn / abandoned King William, VAPJM Mar 2022target 2026
Solar project V2-045, Northampton County
Solar
20.0 MWWithdrawn / abandoned Northampton, VAPJM Jul 2009target 2011
Solar project AH1-079, Middlesex County
Solar
20.0 MWWithdrawn / abandoned Middlesex, VAPJM Jul 2021target 2024
Solar project AD1-078, Orange County
Solar
20.0 MWWithdrawn / abandoned Orange, VAPJM Sep 2017target 2019
Solar project AE2-080, Surry County
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM Feb 2019target 2021
Solar project AH1-179, Shenandoah County
Solar · Valley Overlook Solar, LLC
20.0 MWWithdrawn / abandoned Shenandoah, VAPJM Aug 2021target 2022
Turner I Solar
Solar
20.0 MWWithdrawn / abandoned Henrico, VAPJM Aug 2017target 2022
Solar project AD1-080, Rockingham County
Solar
20.0 MWWithdrawn / abandoned Rockingham, VAPJM Sep 2017target 2019
Battery storage project AE2-052, Prince George County
Battery storage
20.0 MWWithdrawn / abandoned Prince George, VAPJM Jan 2019target 2021
Solar project AC2-096, Pulaski County
Solar
20.0 MWWithdrawn / abandoned Pulaski, VAPJM Mar 2017target 2018
Oak Grove II
Solar
20.0 MWWithdrawn / abandoned Westmoreland, VAPJM Jul 2017target 2021
Solar project AI2-032, Dinwiddie County
Solar
20.0 MWWithdrawn / abandoned Dinwiddie, VAPJM Jan 2023target 2024
Solar project W1-009, Accomack County
Solar
20.0 MWWithdrawn / abandoned Accomack, VAPJM Feb 2010target 2011
Battery storage project AE2-053, Mecklenburg County
Battery storage · RWE Solar Development, LLC
20.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Feb 2019target 2021
Battery storage project AH1-048, Warren County
Battery storage
20.0 MWWithdrawn / abandoned Warren, VAPJM Jul 2021target 2024
Solar project AE1-017, Pulaski County
Solar
20.0 MWWithdrawn / abandoned Pulaski, VAPJM May 2018target 2020
TWE Chesapeake Solar
Solar
20.0 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Aug 2016target 2018
Rives Road Solar
Solar
19.7 MWWithdrawn / abandoned Prince George, VAPJM Sep 2017target 2020
Page 14 of 18

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)