United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

SOLAR + STORAGE Β· PJM

Solar + storage project AG2-102, Accomack County

Solar + storage project AG2-102, Accomack County is a 20.0 MW solar + storage request withdrawn in the PJM interconnection queue, in Accomack County, Virginia, connecting to ODEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-102
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ODEC
Connection point (POI)
Oak Hall-Perdue 69 kV
Location
Accomack County, Virginia
Technology
Solar: 20.0 MW Β· Battery
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
28 January 2021
Proposed online date
June 2024
Withdrawn
December 2024

Location

Marker shows the centre of Accomack County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Accomack County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem