Requests shown64684.7 GW
Active in queue33.8 GW154 requests
Agreement signed4,095 MW25 requests
Withdrawn64684.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

646 requests · page 13 of 13
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 526, Emery County
Solar
3.0 MWWithdrawn / abandoned Emery, UTWest Oct 2013target 2014
Solar project 388, Iron County
Solar
3.0 MWWithdrawn / abandoned Iron, UTWest May 2011target 2011
Solar project 487, Iron County
Solar
3.0 MWWithdrawn / abandoned Iron, UTWest Mar 2013target 2014
Solar project TCS-36, Box Elder County
Solar
3.0 MWWithdrawn / abandoned Box Elder, UTWest Jun 2019target 2021
Solar project 583, Juab County
Solar · PacifiCorp Energy
3.0 MWWithdrawn / abandoned Juab, UTWest Jun 2014target 2016
Solar project 1132, Box Elder County
Solar
3.0 MWWithdrawn / abandoned Box Elder, UTWest Apr 2019target 2021
Solar project 504, Beaver County
Solar
2.9 MWWithdrawn / abandoned Beaver, UTWest Jun 2013target 2015
Solar project 521, Washington County
Solar
2.9 MWWithdrawn / abandoned Washington, UTWest Oct 2013target 2015
Solar project 451, Iron County
Solar
2.9 MWWithdrawn / abandoned Iron, UTWest Jan 2013target 2016
Solar project 503, Beaver County
Solar
2.9 MWWithdrawn / abandoned Beaver, UTWest Jun 2013target 2013
Solar project 519, Washington County
Solar
2.9 MWWithdrawn / abandoned Washington, UTWest Oct 2013target 2015
Gas project 841, Davis County
Gas
2.8 MWWithdrawn / abandoned Davis, UTWest Dec 2016target 2018
Other project 332, Beaver County
Other · PacifiCorp Energy
2.8 MWWithdrawn / abandoned Beaver, UTWest Apr 2010target 2011
Solar project 1113, Emery County
Solar
2.8 MWWithdrawn / abandoned Emery, UTWest Feb 2019target 2019
Other project 500, Utah County
Other
2.6 MWWithdrawn / abandoned Utah, UTWest Jun 2013target 2013
Other project 159, Utah County
Other · PacifiCorp Commercial & Trading
2.5 MWWithdrawn / abandoned Utah, UTWest Aug 2007target 2010
Solar project 584-A, Utah County
Solar
2.2 MWWithdrawn / abandoned Utah, UTWest Jun 2014target 2016
Solar project 457, Beaver County
Solar · Long Ridge Wind, LLP
2.1 MWWithdrawn / abandoned Beaver, UTWest Jan 2013target 2015
Solar project 456, Beaver County
Solar
2.1 MWWithdrawn / abandoned Beaver, UTWest Jan 2013target 2016
Solar project C3-070, Weber County
Solar
2.0 MWWithdrawn / abandoned Weber, UTWest May 2023target 2024
Solar project 955, Iron County
Solar
2.0 MWWithdrawn / abandoned Iron, UTWest Oct 2017target 2018
Hydro project 339, Washington County
Hydro
2.0 MWWithdrawn / abandoned Washington, UTWest Jun 2010target 2020
Solar project C3-074, Millard County
Solar
2.0 MWWithdrawn / abandoned Millard, UTWest May 2023target 2023
Solar project 615, Washington County
Solar
2.0 MWWithdrawn / abandoned Washington, UTWest Aug 2014target 2015
Solar project 494, Millard County
Solar · Bevan's Point Holdings, LLC
2.0 MWWithdrawn / abandoned Millard, UTWest Mar 2013target 2013
Onshore wind project 405, Tooele County
Onshore wind · Tasco Energy, LLC
1.6 MWWithdrawn / abandoned Tooele, UTWest Oct 2011target 2013
Hydro project 417, Sanpete County
Hydro
1.4 MWWithdrawn / abandoned Sanpete, UTWest Mar 2012target 2012
Solar project TCS-35, Box Elder County
Solar
1.0 MWWithdrawn / abandoned Box Elder, UTWest Jun 2019target 2021
Solar project 628, Salt Lake County
Solar
1.0 MWWithdrawn / abandoned Salt Lake, UTWest Oct 2014target 2015
Solar project 596, Beaver County
Solar
1.0 MWWithdrawn / abandoned Beaver, UTWest Jul 2014target 2015
Solar project 625, Sevier County
Solar · South Valley Sustainability Park
1.0 MWWithdrawn / abandoned Sevier, UTWest Oct 2014target 2016
Solar project 1145, Box Elder County
Solar
1.0 MWWithdrawn / abandoned Box Elder, UTWest Jun 2019target 2021
Hydro project 149, Salt Lake County
Hydro · BP Alternative Energy North America, Inc.
0.8 MWWithdrawn / abandoned Salt Lake, UTWest Jul 2007target 2008
Solar project 1152, Utah County
Solar
0.7 MWWithdrawn / abandoned Utah, UTWest Jul 2019
Solar project 215, Tooele County
Solar
0.7 MWWithdrawn / abandoned Tooele, UTWest Apr 2008target 2008
Onshore wind project 334, Beaver County
Onshore wind
0.5 MWWithdrawn / abandoned Beaver, UTWest May 2010target 2010
Solar project 546, Sevier County
Solar
0.5 MWWithdrawn / abandoned Sevier, UTWest Feb 2014target 2014
Other project 390, Beaver County
Other
0.4 MWWithdrawn / abandoned Beaver, UTWest May 2011target 2011
Solar project 1026, Salt Lake County
Solar
0.4 MWWithdrawn / abandoned Salt Lake, UTWest May 2018target 2018
Solar project 1187, Grand County
Solar
0.3 MWWithdrawn / abandoned Grand, UTWest Oct 2019target 2020
Hydro project 704, Cache County
Hydro
0.2 MWWithdrawn / abandoned Cache, UTWest Aug 2015target 2016
Hydro project 686, Cache County
Hydro
0.2 MWWithdrawn / abandoned Cache, UTWest Jul 2015target 2016
Solar project 252, Davis County
Solar
0.2 MWWithdrawn / abandoned Davis, UTWest Nov 2008target 2009
Hydro project 908, Davis County
Hydro
0.2 MWWithdrawn / abandoned Davis, UTWest Jul 2017target 2018
Other project 428, Box Elder County
Other · Entiv Organic, LLC
0.2 MWWithdrawn / abandoned Box Elder, UTWest Jul 2012target 2012
Battery storage project 965, Davis County
Battery storage
0.0 MWWithdrawn / abandoned Davis, UTWest Oct 2017target 2017
Page 13 of 13

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)