🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in New Jersey — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown88792.3 GW
Active in queue16.0 GW71 requests
Agreement signed1,225 MW24 requests
Withdrawn88792.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

887 requests · page 11 of 18
ProjectCapacityStatusLocationRegionQueuedOnline
Stewartstown Generating Facility
Solar
8.0 MWWithdrawn / abandoned Salem, NJPJM Dec 2009target 2010
Roy Road Solar Farm
Solar
8.0 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2014
Solar project W4-067, Sussex County
Solar
8.0 MWWithdrawn / abandoned Sussex, NJPJM Jan 2011target 2012
Valley Road Solar
Solar
8.0 MWWithdrawn / abandoned Somerset, NJPJM Jun 2011target 2013
Battery storage project AA2-063, Sussex County
Battery storage
8.0 MWWithdrawn / abandoned Sussex, NJPJM Feb 2015target 2015
Solar project Y1-046, Monmouth County
Solar
8.0 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2012target 2013
Allerton Road Solar Farm
Solar
8.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jan 2012target 2015
Solar project W3-144, Warren County
Solar
8.0 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2012
Solar project X3-085, Sussex County
Solar
8.0 MWWithdrawn / abandoned Sussex, NJPJM Oct 2011target 2013
Alpha Solar Farm
Solar
8.0 MWWithdrawn / abandoned Warren, NJPJM Jul 2010target 2014
New Village Solar Farm
Solar
8.0 MWWithdrawn / abandoned Warren, NJPJM Aug 2010target 2014
Battery storage project AA2-065, Warren County
Battery storage
8.0 MWWithdrawn / abandoned Warren, NJPJM Feb 2015target 2015
Solar project AG2-257, Ocean County
Solar
8.0 MWWithdrawn / abandoned Ocean, NJPJM Mar 2021target 2022
Solar project W4-055, Warren County
Solar
8.0 MWWithdrawn / abandoned Warren, NJPJM Jan 2011target 2012
Solar project X3-080, Cumberland County
Solar
8.0 MWWithdrawn / abandoned Cumberland, NJPJM Oct 2011target 2012
Solar project AG2-177, Sussex County
Solar
8.0 MWWithdrawn / abandoned Sussex, NJPJM Feb 2021target 2022
Morris Solar Farm
Solar
8.0 MWWithdrawn / abandoned Sussex, NJPJM Mar 2011target 2014
Solar project AG2-256, Somerset County
Solar
8.0 MWWithdrawn / abandoned Somerset, NJPJM Mar 2021target 2022
Millstone Solar Farm
Solar
8.0 MWWithdrawn / abandoned Monmouth, NJPJM Oct 2010target 2016
Solar project AF2-167, Monmouth County
Solar
8.0 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2020target 2021
Solar project X2-001, Monmouth County
Solar
8.0 MWWithdrawn / abandoned Monmouth, NJPJM May 2011target 2012
Solar project X3-013, Cape May County
Solar
8.0 MWWithdrawn / abandoned Cape May, NJPJM Aug 2011target 2012
Minotola 2 Solar Facility
Solar
7.9 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2010target 2018
Solar project X1-008, Warren County
Solar
7.8 MWWithdrawn / abandoned Warren, NJPJM Feb 2011target 2011
Solar project W3-131, Warren County
Solar
7.6 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2011
Solar project W2-051, Salem County
Solar
7.6 MWWithdrawn / abandoned Salem, NJPJM Jul 2010target 2011
Gas project AD1-019, Atlantic County
Gas
7.6 MWWithdrawn / abandoned Atlantic, NJPJM May 2017target 2019
Gas project AA1-075, Atlantic County
Gas
7.5 MWWithdrawn / abandoned Atlantic, NJPJM Oct 2014target 2015
Gas project AB1-030, Atlantic County
Gas
7.5 MWWithdrawn / abandoned Atlantic, NJPJM Jul 2015target 2016
Other project W3-034, Atlantic County
Other
7.5 MWWithdrawn / abandoned Atlantic, NJPJM Aug 2010target 2012
Solar project W2-047, Salem County
Solar
7.5 MWWithdrawn / abandoned Salem, NJPJM Jun 2010target 2011
Solar project AD2-037, Hunterdon County
Solar
7.5 MWWithdrawn / abandoned Hunterdon, NJPJM Jan 2018target 2019
Other project W3-033, Atlantic County
Other
7.5 MWWithdrawn / abandoned Atlantic, NJPJM Aug 2010target 2018
Solar project AD2-006, Hunterdon County
Solar
7.5 MWWithdrawn / abandoned Hunterdon, NJPJM Nov 2017target 2018
Blackwood Solar
Solar
7.3 MWWithdrawn / abandoned Camden, NJPJM Oct 2010target 2012
Gloucester Solar Farm
Solar
7.3 MWWithdrawn / abandoned Camden, NJPJM Jul 2014target 2015
Recovery Road Solar Farm
Solar
7.1 MWWithdrawn / abandoned Burlington, NJPJM Nov 2013target 2018
Solar project W2-037, Burlington County
Solar
7.0 MWWithdrawn / abandoned Burlington, NJPJM Jun 2010target 2011
Other project J04, Burlington County
Other
7.0 MWWithdrawn / abandoned Burlington, NJPJM Oct 2002target 2004
Solar project AE2-082, Monmouth County
Solar
7.0 MWWithdrawn / abandoned Monmouth, NJPJM Jan 2019target 2019
Frankford Solar Farm
Solar
7.0 MWWithdrawn / abandoned Sussex, NJPJM Apr 2011target 2014
Solar project W1-096, Cape May County
Solar
7.0 MWWithdrawn / abandoned Cape May, NJPJM Apr 2010target 2011
Solar project AD1-030, Burlington County
Solar
7.0 MWWithdrawn / abandoned Burlington, NJPJM Jul 2017target 2018
Dotoli Solar Farm
Solar
7.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jan 2011target 2014
Battery storage project AA2-062, Sussex County
Battery storage
7.0 MWWithdrawn / abandoned Sussex, NJPJM Feb 2015target 2015
Solar project W3-035, Gloucester County
Solar
7.0 MWWithdrawn / abandoned Gloucester, NJPJM Aug 2010target 2012
Solar project AG1-496, Hunterdon County
Solar
6.6 MWWithdrawn / abandoned Hunterdon, NJPJM Sep 2020target 2021
Solar project X1-026, Ocean County
Solar
6.3 MWWithdrawn / abandoned Ocean, NJPJM Mar 2011target 2011
Gas project L12, Essex County
Gas
6.2 MWWithdrawn / abandoned Essex, NJPJM Dec 2003target 2004
Solar project W2-017, Salem County
Solar
6.0 MWWithdrawn / abandoned Salem, NJPJM May 2010target 2012
Page 11 of 18

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)