SOLAR Β· PJM

Solar project AG2-257, Ocean County

Solar project AG2-257, Ocean County is a 8.0 MW solar request withdrawn in the PJM interconnection queue, in Ocean County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedApr 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-257
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Location
Ocean County, New Jersey
Technology
Solar: 8.0 MW
Total requested
8.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
18 March 2021
Proposed online date
September 2022
Withdrawn
April 2021

Location

Marker shows the centre of Ocean County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Ocean County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem