πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

OTHER Β· PJM

Other project J04, Burlington County

Other project J04, Burlington County is a 7.0 MW other request withdrawn in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2002 (completed)
  2. Withdrawn / abandonedAug 2004 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J04
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Bustleton 138kV
Location
Burlington County, New Jersey
Technology
Other: 7.0 MW
Total requested
7.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Withdrawn
Queue status
Withdrawn
Entered queue
18 October 2002
Proposed online date
November 2004
Withdrawn
August 2004

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Burlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem