Solar project AD2-037, Hunterdon County

Solar project AD2-037, Hunterdon County is a 7.5 MW solar request withdrawn in the PJM interconnection queue, in Hunterdon County, New Jersey, connecting to JCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2018 (completed)
  2. Withdrawn / abandonedJan 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD2-037
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Gilbert-Morris Park 34.5 kV
Location
Hunterdon County, New Jersey
Technology
Solar: 7.5 MW
Total requested
7.5 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
18 January 2018
Proposed online date
June 2019
Withdrawn
January 2018

Location

Marker shows the centre of Hunterdon County; the queue data does not give exact sites.