WIND Β· OPERATIONAL

Slieve Rushen

Slieve Rushen is a 54 MW onshore wind farm in Northern Ireland, operated by WPO UK Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Northern Ireland
Project stageOperating
  1. PlanningNov 2004 (completed)
  2. ConsentedOct 2006 (completed)
  3. Construction (completed)
  4. OperatingApr 2008 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
54 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
WPO UK Services
Region
Northern Ireland
Country
Northern Ireland
Grid connection (DUKES)
LV
Combined heat & power
No
Coordinates
54.1903, -7.6284

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Slieve Rushen compares

98th of 488largest wind farms in the UK register
2nd of 32in Northern Ireland
0.18%of listed UK wind farms capacity
β‰ˆ 123 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 54 MW station would generate roughly 123 GWh of electricity in a year, similar to the annual use of about 45,550 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Northern Ireland All run by WPO UK Services

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Slieve Rushen Extension
Developer / operator
Unknown
Planning authority
Fermanagh and Omagh
Planning reference
L/2004/2058/F
Application submitted
4 November 2004
Permission granted
1 October 2006
Began operating
15 April 2008
Capacity in planning record
54 MW
Address
Slieve Rushen Derrylin Fermanagh, Co. Fermanagh
REPD reference
4504

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.