WIND Β· OPERATIONAL

Slieve Divena

Slieve Divena is a 30 MW onshore wind farm in Northern Ireland, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Northern Ireland

Key facts

Installed capacity
30 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Greencoat Capital
Region
Northern Ireland
Country
Northern Ireland
Grid connection (DUKES)
LV
Combined heat & power
No
Coordinates
54.5086, -7.1064

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Slieve Divena compares

160th of 488largest wind farms in the UK register
6th of 32in Northern Ireland
0.10%of listed UK wind farms capacity
β‰ˆ 68 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 30 MW station would generate roughly 68 GWh of electricity in a year, similar to the annual use of about 25,310 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Northern Ireland All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Slieve Divena Phase 1 Wind Farm
Developer / operator
Greencoat (formerly Infinis/SSE)
Planning authority
Fermanagh and Omagh
Planning reference
K/2005/0597/F
Application submitted
1 March 2005
Permission granted
17 May 2007
Began operating
10 March 2009
Capacity in planning record
30 MW
Address
Slieve Divena Sixmilecross Beragh Ballygawley County Tyrone, Co. Tyrone
REPD reference
3245

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.