Slieve Divena 2
Slieve Divena 2 is a 18.8 MW onshore wind farm in Northern Ireland, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- Northern Ireland
Key facts
- Installed capacity
- 18.8 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Greencoat Capital
- Region
- Northern Ireland
- Country
- Northern Ireland
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Coordinates
- 54.5086, -7.1064
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Slieve Divena 2 compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 18.8 MW station would generate roughly 43 GWh of electricity in a year, similar to the annual use of about 15,860 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in Northern Ireland All run by Greencoat CapitalNearby generating sites
- Slieve Divena Β· 30 MW onshore wind farm0.0 km
- Shantavny Β· 16.1 MW onshore wind farm1.8 km
- Lendrums Bridge Wind Farm (NI) Β· 5.94 MW onshore wind farm13.8 km
- Screggagh Β· 20 MW onshore wind farm15.5 km
- Lendrums Bridge Extension Wind Farm (NI) Β· 7.3 MW onshore wind farm17.0 km
- Bessy Bell Windfarm (NI) Limited Β· 9 MW onshore wind farm26.0 km
- Tappaghan Wind Farm Β· 28.5 MW onshore wind farm29.2 km
- Dale Farm Β· 5 MW solar farm30.2 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Slieve Divena Phase 2 Wind Farm
- Developer / operator
- Scottish and Southern Energy (SSE)
- Planning authority
- Fermanagh and Omagh
- Planning reference
- K/2005/1691/F
- Application submitted
- 13 September 2005
- Permission granted
- 6 June 2007
- Construction started
- 30 May 2016
- Began operating
- 16 February 2017
- Capacity in planning record
- 18.8 MW
- Address
- Slieve Divena Wind Farm Phase II in the townlands of Altcloghfin, Altamuskin and Shantavny Irish, Co Tyrone, Co. Tyrone, BT79
- REPD reference
- 4054
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.