WIND Β· OPERATIONAL

Pant y Wal

Pant y Wal is a 52.5 MW onshore wind farm in Wales, operated by Pennant Walters. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Wales
Project stageOperating
  1. PlanningMar 2006 (completed)
  2. ConsentedMay 2011 (completed)
  3. ConstructionApr 2012 (completed)
  4. OperatingJun 2013 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
52.5 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Pennant Walters
Region
Wales
Country
Wales
Grid connection (DUKES)
HV
Combined heat & power
No
Postcode
CF35 6ED
Coordinates
51.6129, -3.5050

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Pant y Wal compares

102nd of 488largest wind farms in the UK register
8th of 43in Wales
0.18%of listed UK wind farms capacity
β‰ˆ 120 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 52.5 MW station would generate roughly 120 GWh of electricity in a year, similar to the annual use of about 44,290 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Wales All run by Pennant Walters

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
Pennant Wind Energy Ventures (PWEV)
Planning authority
Bridgend
Planning reference
P/06/417/FUL
Application submitted
31 March 2006
Permission granted
4 May 2011
Construction started
1 April 2012
Began operating
1 June 2013
Capacity in planning record
25 MW
Address
Mynydd Maesteg, Mynydd Pwlle yr Helog, Ogmore Vale, Rhondda Valley, Mid Glamorgan
REPD reference
4039

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.