πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
WIND Β· OPERATIONAL

Maesgwyn Extension

Maesgwyn Extension is a 2.5 MW onshore wind farm in Wales, operated by Pennant Walters. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Wales
Project stageOperating
  1. PlanningAug 2014 (completed)
  2. ConsentedDec 2015 (completed)
  3. ConstructionJan 2016 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
2.5 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Pennant Walters
Region
Wales
Country
Wales
Grid connection (DUKES)
HV
Combined heat & power
No
Coordinates
51.7406, -3.6442

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Maesgwyn Extension compares

457th of 488largest wind farms in the UK register
41st of 43in Wales
0.01%of listed UK wind farms capacity
β‰ˆ 5.7 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 2.5 MW station would generate roughly 5.7 GWh of electricity in a year, similar to the annual use of about 2,110 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Wales All run by Pennant Walters

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Maesgwyn Wind Farm - extension
Developer / operator
Pennant Walters (MAESX) Limited
Planning authority
Neath Port Talbot
Planning reference
P2014/0733
Application submitted
15 August 2014
Permission granted
17 December 2015
Construction started
21 January 2016
Began operating
29 March 2016
Capacity in planning record
2.5 MW
Address
Maesgwyn Wind Farm Between Onllwyn & Glynneath, West Glamorgan
REPD reference
4485

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.