Dummuies
Dummuies is a 12.3 MW onshore wind farm in Scotland, operated by WPO UK Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- Scotland
Key facts
- Installed capacity
- 12.3 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- WPO UK Services
- Region
- Scotland
- Country
- Scotland
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Coordinates
- 57.4511, -2.6915
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Dummuies compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 12.3 MW station would generate roughly 28 GWh of electricity in a year, similar to the annual use of about 10,330 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in Scotland All run by WPO UK ServicesNearby generating sites
- Glens of Foudland Β· 26 MW onshore wind farm4.2 km
- Clashindarroch Β· 36.9 MW onshore wind farm10.4 km
- Cairnborrow Wind Energy Ltd Β· 10.3 MW onshore wind farm12.5 km
- Gordonstown Hill Β· 12.5 MW onshore wind farm12.5 km
- Boyndie Β· 16.3 MW onshore wind farm22.3 km
- Kildrummy Β· 18.4 MW onshore wind farm25.1 km
- Boganlea Β· 2.31 MW onshore wind farm26.7 km
- Dorenell Β· 177 MW onshore wind farm28.6 km
Also operated by WPO UK Services
WPO UK Services operates 38 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Dummuie
- Developer / operator
- Tetro Energy Ltd (ECO2)
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2003/0084
- Application submitted
- 20 August 2003
- Permission granted
- 20 February 2004
- Construction started
- 1 June 2006
- Began operating
- 1 January 2007
- Capacity in planning record
- 12.3 MW
- Address
- East Dummuie Huntly, Grampian
- REPD reference
- 3200
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.