Boganlea
Boganlea is a 2.31 MW onshore wind farm in Scotland, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- Scotland
Key facts
- Installed capacity
- 2.31 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Greencoat Capital
- Region
- Scotland
- Country
- Scotland
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- AB53 5UY
- Coordinates
- 57.5663, -2.2999
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Boganlea compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 2.31 MW station would generate roughly 5.3 GWh of electricity in a year, similar to the annual use of about 1,950 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in Scotland All run by Greencoat CapitalNearby generating sites
- Gordonstown Hill Β· 12.5 MW onshore wind farm15.9 km
- Boyndie Β· 16.3 MW onshore wind farm20.2 km
- Glens of Foudland Β· 26 MW onshore wind farm25.9 km
- Dummuies Β· 12.3 MW onshore wind farm26.7 km
- Hill of Fiddes Β· 6.9 MW onshore wind farm30.6 km
- Peterhead Β· 1,180 MW gas-fired power station32.1 km
- Clashindarroch Β· 36.9 MW onshore wind farm36.2 km
- Cairnborrow Wind Energy Ltd Β· 10.3 MW onshore wind farm37.6 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Bogenlea Farm
- Developer / operator
- Eco2
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2009/1541
- Application submitted
- 20 May 2009
- Permission granted
- 10 December 2009
- Construction started
- 1 October 2013
- Began operating
- 18 August 2014
- Capacity in planning record
- 2.3 MW
- Address
- New Byth, Turriff. AB53 5UY, Grampian
- REPD reference
- 4346
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source