Project stageOperating
  1. PlanningAug 2014 (completed)
  2. ConsentedOct 2014 (completed)
  3. ConstructionApr 2016 (completed)
  4. OperatingJul 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.66 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
BS24 6RR
Coordinates
51.2871, -2.9813

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Wick Road compares

479th of 662largest solar farms in the UK register
115th of 192in South West
0.08%of listed UK solar farms capacity
β‰ˆ 4.1 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.66 MW station would generate roughly 4.1 GWh of electricity in a year, similar to the annual use of about 1,510 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Wick Farm Solar Park
Developer / operator
Hadstone Energy/ Communities for Renewables
Planning authority
Somerset
Planning reference
05/14/00019
Application submitted
20 August 2014
Permission granted
28 October 2014
Construction started
1 April 2016
Began operating
1 July 2016
Capacity in planning record
14.6 MW
Address
S/O Wick Farm, Brean Road, Lympsham, Weston Super Mare, North Somerset, Somerset, BS24 0HD
REPD reference
2274

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.