SOLAR Β· OPERATIONAL

Pilkington

Pilkington is a 2.3 MW solar farm in North West England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • North West
  • England
Project stageOperating
  1. PlanningApr 2018 (completed)
  2. ConsentedJul 2018 (completed)
  3. ConstructionApr 2019 (completed)
  4. OperatingApr 2019 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
2.3 MW
Status
Operational
Technology
Solar Β· PV
Operator
Lightsource BP
Region
North West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
L40 7TB
Coordinates
53.5735, -2.8147

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Pilkington compares

603rd of 662largest solar farms in the UK register
23rd of 23in North West
0.04%of listed UK solar farms capacity
β‰ˆ 2.0 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 2.3 MW station would generate roughly 2.0 GWh of electricity in a year, similar to the annual use of about 750 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in North West All run by Lightsource BP

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Lathom (Pilkington Technical Centre)
Developer / operator
Lightsource BP
Planning authority
West Lancashire
Planning reference
2018/0409/FUL
Application submitted
17 April 2018
Permission granted
31 July 2018
Construction started
1 April 2019
Began operating
16 April 2019
Capacity in planning record
2.5 MW
Address
Land To The E/O Lords Cottage, Hall Lane, Lathom, Ormskirk, Lancashire, L40 6JB
REPD reference
6513

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.