Ollerton
Ollerton is a 4.25 MW solar farm in East Midlands England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- East Midlands
- England
Key facts
- Installed capacity
- 4.25 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- East Midlands
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- NG22 9DX
- Coordinates
- 53.1874, -1.0553
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Ollerton compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.25 MW station would generate roughly 3.7 GWh of electricity in a year, similar to the annual use of about 1,380 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in East Midlands All run by AnescoNearby generating sites
- Stud Farm Β· 2.37 MW solar farm4.3 km
- Eakring Β· 11.8 MW solar farm4.6 km
- Bilsthorpe Β· 5.74 MW solar farm4.8 km
- Bilsthorpe Β· 10.3 MW onshore wind farm4.9 km
- Thoresby Β· 19.8 MW solar farm5.1 km
- Welbeck Β· 11.3 MW solar farm6.8 km
- Welbeck Β· 16 MW solar farm7.2 km
- Westwood Farm Β· 5.15 MW solar farm9.4 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Land South Off Ollerton Road
- Developer / operator
- Anesco
- Planning authority
- Newark and Sherwood
- Planning reference
- 15/00875/FULM
- Application submitted
- 22 May 2015
- Permission granted
- 7 June 2016
- Construction started
- 15 October 2016
- Began operating
- 15 January 2017
- Capacity in planning record
- 4.2 MW
- Address
- Land South Off, Ollerton Road, Edwinstowe, Mansfield, Nottinghamshire, NG21 9Q
- REPD reference
- 5293
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.