Nancrossa
Nancrossa is a 6.86 MW solar farm in South West England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 6.86 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- TR10 9EA
- Coordinates
- 50.1614, -5.1845
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Nancrossa compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 6.86 MW station would generate roughly 6.0 GWh of electricity in a year, similar to the annual use of about 2,230 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by AnescoNearby generating sites
- Little T Β· 5.44 MW solar farm2.2 km
- Roskrow Barton Β· 1.7 MW onshore wind farm4.2 km
- Pencoose Β· 8.14 MW solar farm4.3 km
- Wheal Jane Β· 1.42 MW solar farm9.5 km
- Goonhilly Downs Wind Farm Β· 12 MW onshore wind farm12.8 km
- Goonhilly Solar Β· 4.51 MW solar farm13.0 km
- Churchtown Farm Solar Β· 4.99 MW solar farm14.5 km
- Higher Trenhayle Β· 2.93 MW solar farm14.5 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Nancrossa Farm solar park
- Developer / operator
- Second Solar Project
- Planning authority
- Cornwall
- Planning reference
- PA14/04493
- Application submitted
- 14 May 2014
- Permission granted
- 8 September 2015
- Construction started
- 5 January 2016
- Began operating
- 31 March 2016
- Capacity in planning record
- 6 MW
- Address
- Nancrossa Farm Rame Cross Penryn Cornwall, Cornwall, TR10 9EA
- REPD reference
- 2126
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.