Howton
Howton is a 5 MW solar farm in South West England, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 5 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- PL12 6QY
- Coordinates
- 50.4424, -4.2820
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Howton compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by Lightsource BPNearby generating sites
- North Wayton Β· 8.4 MW solar farm4.6 km
- Newton Ferrers Β· 19.5 MW solar farm5.1 km
- Bake Farm Β· 5 MW solar farm6.4 km
- Bake Farm Β· 5 MW solar farm6.4 km
- Wilton Β· 9.48 MW solar farm7.6 km
- High Down Β· 0.5 MW onshore wind farm9.7 km
- Mendennick Solar Β· 2.64 MW solar farm10.1 km
- Trefinnick Β· 4.4 MW solar farm12.1 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Howton Farm
- Developer / operator
- Low carbon Solar Partners
- Planning authority
- Cornwall
- Planning reference
- PA11/00311
- Application submitted
- 14 January 2011
- Permission granted
- 18 April 2011
- Began operating
- 22 July 2011
- Capacity in planning record
- 4.4 MW
- Address
- Howton Farm Pillaton Saltash Cornwall, Cornwall, PL12 6QY
- REPD reference
- 1021
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.