North Wayton
North Wayton is a 8.4 MW solar farm in South West England, operated by Octopus Investments. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 8.4 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Octopus Investments
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- PL12 6QQ
- Coordinates
- 50.4420, -4.2170
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How North Wayton compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 8.4 MW station would generate roughly 7.4 GWh of electricity in a year, similar to the annual use of about 2,730 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by Octopus InvestmentsNearby generating sites
- Howton Β· 5 MW solar farm4.6 km
- Newton Ferrers Β· 19.5 MW solar farm8.6 km
- Mendennick Solar Β· 2.64 MW solar farm9.3 km
- Bake Farm Β· 5 MW solar farm10.3 km
- Bake Farm Β· 5 MW solar farm10.3 km
- Wilton Β· 9.48 MW solar farm11.7 km
- Newnham Β· 11.6 MW solar farm13.3 km
- Lee Moor Β· 4.99 MW solar farm13.4 km
Also operated by Octopus Investments
Octopus Investments operates 134 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- North Wayton Farm
- Developer / operator
- KS SPV21 Ltd
- Planning authority
- Cornwall
- Planning reference
- PA12/09275
- Application submitted
- 9 October 2012
- Permission granted
- 9 April 2013
- Began operating
- 31 March 2014
- Capacity in planning record
- 5 MW
- Address
- Landulph Saltash Cornwall, Cornwall, PL12 6QQ
- REPD reference
- 1776
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source