SOLAR Β· OPERATIONAL

Cwrt Henllys

Cwrt Henllys is a 4.99 MW solar farm in Wales, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • Wales
Project stageOperating
  1. PlanningJul 2015 (completed)
  2. ConsentedJun 2016 (completed)
  3. ConstructionOct 2016 (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.99 MW
Status
Operational
Technology
Solar Β· PV
Operator
Lightsource BP
Region
Wales
Country
Wales
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
NP44 7AS
Coordinates
51.6168, -3.0664

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Cwrt Henllys compares

351st of 662largest solar farms in the UK register
35th of 75in Wales
0.09%of listed UK solar farms capacity
β‰ˆ 4.4 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.99 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in Wales All run by Lightsource BP

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Cwrt Henllys Farm
Developer / operator
Lightsource Renewable Energy
Planning authority
Torfaen
Planning reference
15/P/00434
Application submitted
22 July 2015
Permission granted
16 June 2016
Construction started
29 October 2016
Began operating
29 December 2016
Capacity in planning record
5 MW
Address
Church Farm, Cwm Lane, Henllys, Cwmbran, Gwent, NP44 7AS
REPD reference
5524

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026