Crumlin
Crumlin is a 4.55 MW solar farm in Wales, operated by WPO UK Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- Wales
Key facts
- Installed capacity
- 4.55 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- WPO UK Services
- Region
- Wales
- Country
- Wales
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Coordinates
- 51.6718, -3.1524
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Crumlin compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.55 MW station would generate roughly 4.0 GWh of electricity in a year, similar to the annual use of about 1,480 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in Wales All run by WPO UK ServicesNearby generating sites
- Darran Β· 1.82 MW solar farm2.6 km
- Penyrheollas Β· 4.99 MW solar farm4.0 km
- Singrug Β· 12 MW solar farm4.3 km
- Hill Farm Β· 7.69 MW solar farm5.1 km
- Hafod CIC Β· 2.78 MW solar farm6.0 km
- Hendai Β· 13.4 MW solar farm8.0 km
- Cwrt Henllys Β· 4.99 MW solar farm8.5 km
- Park Farm West Β· 3.93 MW solar farm12.9 km
Also operated by WPO UK Services
WPO UK Services operates 38 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Upper Pant-Ysgawen Farm/Crumlin
- Developer / operator
- Suncredit UK
- Planning authority
- Caerphilly
- Planning reference
- 15/0512/FULL
- Application submitted
- 22 July 2015
- Permission granted
- 10 September 2015
- Construction started
- 15 February 2016
- Began operating
- 7 December 2016
- Capacity in planning record
- 4.9 MW
- Address
- Pant-Ysgawen Farm, Pant Ysgawen Farm Lane, Newbridge, Newport, Gwent, Caerphilly, NP11 4RJ
- REPD reference
- 5381
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.