Hendai
Hendai is a 13.4 MW solar farm in Wales, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- Wales
Key facts
- Installed capacity
- 13.4 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Greencoat Capital
- Region
- Wales
- Country
- Wales
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- CF82 8FU
- Coordinates
- 51.6725, -3.2683
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Hendai compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 13.4 MW station would generate roughly 12 GWh of electricity in a year, similar to the annual use of about 4,350 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in Wales All run by Greencoat CapitalNearby generating sites
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Hendai Farm
- Developer / operator
- Conergy UK
- Planning authority
- Caerphilly
- Planning reference
- 13/0846/FULL
- Application submitted
- 10 December 2013
- Permission granted
- 10 April 2014
- Construction started
- 1 October 2014
- Began operating
- 1 March 2015
- Capacity in planning record
- 13.4 MW
- Address
- Land At Hendai Farm Heol Adam Gelligaer Hengoed CF82 8FU, Mid Glamorgan, CF82 8FU
- REPD reference
- 2370
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.