SOLAR Β· OPERATIONAL

Burnham Wick

Burnham Wick is a 5 MW solar farm in East of England, England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • East of England
  • England
Project stageOperating
  1. PlanningSep 2014 (completed)
  2. ConsentedJan 2015 (completed)
  3. ConstructionSep 2015 (completed)
  4. OperatingDec 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
5 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
East of England
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
CM0 8LU
Coordinates
51.6272, 0.8430

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Burnham Wick compares

252nd of 662largest solar farms in the UK register
41st of 76in East of England
0.09%of listed UK solar farms capacity
β‰ˆ 4.4 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 5 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in East of England All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Wick Farm (Burnham on Crouch)
Developer / operator
Countryside Renewables
Planning authority
Maldon
Planning reference
14/00775/FUL
Application submitted
9 September 2014
Permission granted
26 January 2015
Construction started
11 September 2015
Began operating
17 December 2015
Capacity in planning record
5 MW
Address
E/O Burnham Wick Farm, Wick Road, Burnham on Crouch, Essex, CM0 8FA, Essex
REPD reference
2268

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.