Bilsborrow
Bilsborrow is a 4.99 MW solar farm in North West England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- North West
- England
Key facts
- Installed capacity
- 4.99 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Greencoat Capital
- Region
- North West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- PR3 0RU
- Coordinates
- 53.8457, -2.7596
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Bilsborrow compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.99 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in North West All run by Greencoat CapitalNearby generating sites
- West Field Β· 4.94 MW solar farm3.0 km
- Orchard End Windfarm Β· 4 MW onshore wind farm9.2 km
- Fell View Β· 4.26 MW solar farm9.8 km
- Grimsargh Β· 2.92 MW solar farm9.8 km
- Wrea Green Β· 4.88 MW solar farm13.8 km
- Staining Wood Β· 5 MW solar farm14.7 km
- Carver Hey Β· 2.51 MW solar farm15.5 km
- Blackburn Β· 60 MW CCGT gas power station20.4 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Bilsborrow Solar Farm
- Developer / operator
- Greencoat Capital
- Planning authority
- Wyre
- Planning reference
- 15/00260/LMAJ
- Application submitted
- 23 March 2015
- Permission granted
- 15 June 2015
- Construction started
- 12 December 2016
- Began operating
- 30 March 2017
- Capacity in planning record
- 5 MW
- Address
- Land Off, Moss Lane, Bilsborrow, Preston,, Lancashire, PR3 0RU
- REPD reference
- 5163
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.