πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
SOLAR Β· OPERATIONAL

Bentham

Bentham is a 11.1 MW solar farm in South West England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • South West
  • England
Project stageOperating
  1. PlanningOct 2013 (completed)
  2. ConsentedDec 2014 (completed)
  3. ConstructionMar 2015 (completed)
  4. OperatingJul 2015 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
11.1 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
South West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
SN5 4JB
Coordinates
51.6055, -1.8987

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Bentham compares

128th of 662largest solar farms in the UK register
26th of 192in South West
0.20%of listed UK solar farms capacity
β‰ˆ 9.7 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 11.1 MW station would generate roughly 9.7 GWh of electricity in a year, similar to the annual use of about 3,590 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in South West All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Bentham Farm
Developer / operator
Hive Energy
Planning authority
Wiltshire
Planning reference
13/04872/FUL
Application submitted
8 October 2013
Permission granted
15 December 2014
Construction started
15 March 2015
Began operating
15 July 2015
Capacity in planning record
8 MW
Address
Bentham Farm, Bentham Lane,Bentham, Purton, Swindon, Wiltshire, Wiltshire, SN5 4JB
REPD reference
2344

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.