Bradenstoke Solar Park Ltd
Bradenstoke Solar Park Ltd is a 69.8 MW solar farm in South West England, operated by Bluefield Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- South West
- England
Key facts
- Installed capacity
- 69.8 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Bluefield Services
- Region
- South West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- SN15 4PZ
- Coordinates
- 51.5066, -1.9680
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Bradenstoke Solar Park Ltd compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 69.8 MW station would generate roughly 61 GWh of electricity in a year, similar to the annual use of about 22,640 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in South West All run by Bluefield ServicesNearby generating sites
- Spittleborough Β· 9.14 MW solar farm7.4 km
- Swindon Β· 60.9 MW solar farm10.7 km
- CommonFarm Β· 3.34 MW solar farm11.8 km
- Bentham Β· 11.1 MW solar farm12.0 km
- Hullavington Β· 8.32 MW solar farm13.6 km
- Newnton Dairy Β· 7.18 MW solar farm16.7 km
- Sandridge Β· 49.6 MW solar farm17.0 km
- Castle Combe Β· 15.3 MW solar farm17.3 km
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Bradenstoke solar park
- Developer / operator
- Defence Infrastructure Organisation / BSR
- Planning authority
- Wiltshire
- Planning reference
- 14/06989/FUL
- Application submitted
- 23 July 2014
- Permission granted
- 13 November 2014
- Construction started
- 1 January 2015
- Began operating
- 21 September 2016
- Capacity in planning record
- 69.8 MW
- Address
- Mod Lyneham, Lyneham, Chippenham, Wiltshire, Wiltshire, SN15 4XX
- REPD reference
- 2203
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.