Project stageOperating
  1. PlanningAug 2015 (completed)
  2. ConsentedNov 2015 (completed)
  3. ConstructionFeb 2016 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
4.99 MW
Status
Operational
Technology
Solar Β· PV
Operator
Greencoat Capital
Region
North West
Country
England
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
BL4 8SJ
Coordinates
53.5331, -2.3760

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Bent Spur compares

351st of 662largest solar farms in the UK register
9th of 23in North West
0.09%of listed UK solar farms capacity
β‰ˆ 4.4 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.99 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in North West All run by Greencoat Capital

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Bent Spur Solar Farm
Developer / operator
Active Renewables
Planning authority
Bolton
Planning reference
94654/15
Application submitted
24 August 2015
Permission granted
20 November 2015
Construction started
20 February 2016
Began operating
31 March 2016
Capacity in planning record
5 MW
Address
Bent Spur Farm, Bent Spur Road, Kearsley, Bolton, Greater Manchester, BL4 8SJ
REPD reference
5723

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.