Arnawood
Arnawood is a 4.99 MW solar farm in North West England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- North West
- England
Key facts
- Installed capacity
- 4.99 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Greencoat Capital
- Region
- North West
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- LA2 0AE
- Coordinates
- 54.0285, -2.8203
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Arnawood compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.99 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in North West All run by Greencoat CapitalNearby generating sites
- Heysham South Wind Farm Β· 7.5 MW onshore wind farm3.1 km
- FannyHouse Β· 4.94 MW solar farm4.6 km
- Heysham 1 Β· 1,060 MW nuclear power station5.2 km
- Heysham 2 Β· 1,240 MW nuclear power station5.2 km
- Orchard End Windfarm Β· 4 MW onshore wind farm14.6 km
- West Field Β· 4.94 MW solar farm17.7 km
- Bilsborrow Β· 4.99 MW solar farm20.7 km
- Walney 04 Β· 329 MW offshore wind farm26.6 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Arna Wood Solar
- Developer / operator
- BE Renewables (on behalf of Arna Wood)
- Planning authority
- Lancaster
- Planning reference
- 14/00907/FUL
- Application submitted
- 18 August 2014
- Permission granted
- 1 July 2015
- Construction started
- 31 January 2017
- Began operating
- 31 March 2017
- Capacity in planning record
- 6.2 MW
- Address
- Arna Wood Farm, East Arna Wood Lane, Lancaster, Lancashire, Lancashire, LA2 0AE
- REPD reference
- 2263
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.