Grid infrastructure › Connection queue › Solar + storage
SOLAR + STORAGE · SHETKeithick 16 Solar & BESS
Keithick 16 Solar & BESS is a 16 MW solar + storage project consented, connecting to the SSEN Transmission (north Scotland) network at Coupar Angus 132/33kV GSP, with capacity due from December 2026. The connection agreement is held by Sirius Ecodev (Keithick) Ltd.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Dec 2026 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-001890
- Customer
- Sirius Ecodev (Keithick) Ltd
- Technology
- Energy Storage System, PV Array (Photo Voltaic/solar)
- Total capacity
- 16 MW
- Change in this agreement
- +16 MW
- Capacity effective from
- 31 December 2026
- Connection site
- Coupar Angus 132/33kV GSP
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Consents Approved
- Connections reform gate
- Gate 2
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Coupar Angus 132/33kV GSP
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem