Coupar Solar Farm

Coupar Solar Farm is a 50 MW solar project in planning, connecting to the SSEN Transmission (north Scotland) network at Coupar Angus 132/33kV GSP, with capacity due from April 2027. The connection agreement is held by Coupar Two Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-001862
Customer
Coupar Two Limited
Technology
PV Array (Photo Voltaic/solar)
Total capacity
50 MW
Change in this agreement
+50 MW
Capacity effective from
30 April 2027
Connection site
Coupar Angus 132/33kV GSP
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Embedded (connects through the local distribution network)
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Coupar Angus Β· Grid map

Other projects at Coupar Angus 132/33kV GSP

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem